|
508 U.S. 602
No. 91-904.
Argued Dec. 1, 1992.
Decided June 14, 1993.
Syllabus [FN*]
FN* The syllabus
constitutes no part of the opinion of the Court but has been prepared by
the Reporter of Decisions for the convenience of the reader.
See United States v. Detroit Lumber Co., 200 U.S. 321, 337, 26 S.Ct.
282, 287, 50 L.Ed. 499.
The
Multiemployer Pension Plan Amendments Act of 1980 (MPPAA) amended the
Employee Retirement Income Security Act of 1974 (ERISA) to provide that in
certain circumstances an employer withdrawing from a multiemployer plan
incurs as "withdrawal liability" a share of the plan's unfunded
vested benefits, 29 U.S.C. §§ 1381, 1391.
Withdrawal liability is assessed by means of a notification by the
"plan sponsor" and a demand for payment. § 1399(b). An unresolved dispute is referred to arbitration,
where (1) the sponsor's factual determinations are "presumed
correct" unless a contesting party "shows by a preponderance of
the evidence that the determination was unreasonable
or clearly erroneous," § 1401(a)(3)(A);
and (2) the sponsor's actuary's calculation of a plan's unfunded
vested benefits is presumed correct unless a contesting party "shows
by a preponderance of the evidence" that, inter alia, "the
actuarial assumptions and methods" used in a calculation "were,
in the aggregate, unreasonable," § 1401(a)(3)(B). Petitioner
Concrete Pipe and Products of California, Inc., is an employer charged
with withdrawal liability by the trustees of respondent, a multiemployer
pension plan (Plan). After
losing in arbitration, Concrete Pipe filed an action to set aside or
modify the arbitrator's decision and raised a constitutional challenge to
the MPPAA, but the District Court granted the Plan's motion to confirm the
award. The Court of
Appeals affirmed.
Held:
1.
The MPPAA does not unconstitutionally deny Concrete Pipe an impartial
adjudicator by placing the determination of withdrawal liability in the
plan sponsor, here the trustees, subject to § 1401's presumptions. Pp. 2276-2286.
(a)
Even assuming that the possibility of trustee bias toward imposing the
greatest possible withdrawal liability would suffice to bar the trustees
from serving as adjudicators of Concrete Pipe's withdrawal liability
because of their fiduciary obligations to beneficiaries of the Plan, the
Due Process Clause is not violated here because the first adjudication in
this case was the arbitration proceeding, not the trustees' initial
liability determination. The trustees' statutory notification
603 and demand obligations are undertaken in an enforcement capacity.
Pp. 2276-2278.
(b)
Nor did the arbitrator's adjudication deny Concrete Pipe its right to
procedural due process. While
the § 1401(a)(3)(A) presumption shifts the burden of persuasion to the
employer, the statute is incoherent with respect to the degree of
certainty required to overturn a plan sponsor's factual determination.
In light of the assumed bias, deference to a plan sponsor's
determination would raise a substantial due process question.
The uncertainty raised by this incoherent statute is resolved by
applying the canon requiring that an ambiguous statute be construed to
avoid serious constitutional problems unless such construction is plainly
contrary to Congress's intent.
Thus, the presumption is construed to place the burden on the
employer to disprove an alleged fact by a preponderance permitting
independent review by the arbitrator of the trustees' factual
determinations. The
approach taken by the arbitrator and courts below in this case is not
inconsistent with this Court's interpretation of the first presumption.
Pp. 2278-2284.
(c)
The § 1401(a)(3)(B) presumption also raises no procedural due process
issue. The assumptions
and methods used in calculating withdrawal liability are selected in the
first instance not by the trustees, but by the plan actuary, § 1393(c),
who is a trained professional subject to regulatory standards.
The technical nature of the assumptions and methods, and the
necessity for applying the same ones in several contexts, limit an
actuary's opportunity to act unfairly toward a withdrawing employer.
Moreover, since § 1401(a)(3)(B) speaks not about the
reasonableness of the trustees' conclusions of historical fact, but about
the aggregate reasonableness of the actuary's assumptions and methods in
calculating the dollar liability figure, an employer's burden to overcome
the presumption is simply to show that an apparently unbiased
professional, whose obligations tend to moderate any claimed inclination
to come down hard on withdrawing employers, has based a calculation on a
combination of methods and assumptions that falls outside the range of
reasonable actuarial practice. Pp. 2284-2286.
2.
The MPPAA, as applied, does not deny substantive due process in violation
of the Fifth Amendment. The
imposition of withdrawal liability is clearly rational here because
Concrete Pipe's liability is based on
a proportion of its contributions during its participation in the
Plan. Pp. 2286-2289.
3.
The MPPAA, as applied, did not take Concrete Pipe's property without just
compensation. The
application of a regulatory statute that is otherwise within Congress's
powers may not be defeated by private contractual provisions, such as
those protecting Concrete Pipe from liability beyond what was specified in
its collective-bargaining and trust
604 agreements. See
Connolly v. Pension Benefit Guaranty Corporation, 475 U.S. 211, 223-224,
106 S.Ct. 1018, 1025, 89 L.Ed.2d 166.
Examining Concrete Pipe's relationship with the Plan in light of
the three factors the Court has said have particular significance for
takings claims confirms this. First, the Government did not physically invade or
permanently appropriate Concrete Pipe's assets for its own use. Second, Concrete Pipe has failed to show that having to
pay out an estimated 46% of shareholder equity is an economic impact out
of proportion to its experience with the Plan, since diminution in a
property's value, however serious, is insufficient to demonstrate a
taking. See, e.g.,
Village of Euclid v. Ambler Realty Co., 272 U.S. 365, 384, 47 S.Ct. 114,
117, 71 L.Ed. 303. Third,
the conditions on its contractual promises did not give Concrete Pipe a
reasonable expectation that it would not be faced with liability for
promised benefits. At the time it began making payments to the Plan,
pension plans had long been subject to federal regulation.
Indeed, withdrawing employers already faced contingent liability
under ERISA, and Concrete Pipe's reliance on ERISA's original limitation
of contingent withdrawal liability to 30% of net worth is misplaced, there
being no reasonable basis to expect that the legislative ceiling would
never be lifted, see Usery v. Turner Elkhorn Mining Co., 428 U.S. 1, 16,
96 S.Ct. 2882, 2893, 49 L.Ed.2d 752.
Pp. 2289-2292.
936
F.2d 576 (CA9 1991), affirmed.
SOUTER,
J., delivered the opinion of the Court, which was unanimous except insofar
as O'CONNOR, J., did not join the statement to which n. 28 is attached,
SCALIA, J., did not join Part III-B-1-b, and THOMAS, J., did not join Part
III-B-1. O'CONNOR, J.,
filed a concurring opinion, post, p. ----.
THOMAS, J., filed an opinion concurring in part and concurring in
the judgment, post, p. ----.
Dennis
R. Murphy, Sacramento, CA, for petitioner.
John
S. Miller, Jr., Los Angeles, CA, for respondent.
Carol
Connor Flowe, Washington, DC, for Pension Ben. Guar. Corp. as amicus
curiae by special leave of the Court.
605
Justice SOUTER delivered the opinion of the Court. [FN1]
FN1. Justice SCALIA
does not join Part III-B-1-b of this opinion.
Respondent Construction Laborers Pension Trust for Southern
California (Plan) is a multiemployer pension trust fund established under
a Trust Agreement executed in 1962.
Petitioner Concrete Pipe and Products of California, Inc. (Concrete
Pipe), is an employer and former contributor to the Plan that withdrew
from it and was assessed "withdrawal liability" under provisions
of the Employee Retirement Income Security Act of 1974 (ERISA), 29 U.S.C.
§§ 1301-1461 (1988 ed. and Supp. III), added by the Multiemployer
Pension Plan Amendments Act of 1980 (MPPAA), Pub.L. 96-364, 94 Stat. 1208. Concrete Pipe contends that the MPPAA's assessment and
arbitration provisions worked to deny it procedural due process.
And, although we have upheld the MPPAA against constitutional
challenge under the substantive component of the Due Process Clause and
the Takings Clause, Pension Benefit Guaranty Corporation v. R.A. Gray
& Co., 467 U.S. 717, 104 S.Ct. 2709, 81 L.Ed.2d 601 (1984); Connolly
v. Pension Benefit Guaranty Corporation, 475 U.S. 211, 106 S.Ct. 1018, 89
L.Ed.2d 166 (1986), Concrete Pipe contends that, as applied to it, the
MPPAA violates these provisions as well.
We see merit in none of Concrete Pipe's contentions.
I
A pension plan like the one in issue, to which more than one
employer contributes, is characteristically maintained to fulfill the
terms of collective-bargaining agreements.
The contributions made by employers participating in such a
multiemployer plan are pooled in a general fund available to pay any
benefit obligation of the plan.
To receive benefits, an 606 employee participating in such a plan need not work for one
employer for any particular continuous period. Because service credit is portable, employees of an
employer participating in the plan may receive such credit for any work
done for any participating employer.
An employee obtains a vested right to secure benefits upon
retirement after accruing a certain length of service for participating
employers; benefits vest
under the Plan in this case when an employee accumulates 10 essentially
continuous years of credit. See
Brief for Petitioner 28.
Multiemployer plans like
the one before us have features that are beneficial in industries where "there [is]
little if any likelihood that individual employers would or could
establish single-employer plans for their employees ...[,] where there are
hundreds and perhaps thousands of small employers, with countless numbers
of employers going in and out of business each year, [and where] the nexus
of employment has focused on the relationship of the workers to the union
to which they belong, and/or the industry in which they are employed,
rather than to any particular employer."
Multiemployer Pension Plan Termination Insurance Program:
Hearings before the Subcommittee on Oversight of the House
Committee on Ways and Means, 96th Cong., 1st Sess., 50 (1979) (statement
of Robert A. Georgine, Chairman, National Coordinating Committee for
Multiemployer Plans).
Multiemployer plans provide
the participating employers with such labor market benefits as the
opportunity to offer a pension program (a significant part of the covered
employees' compensation package) with cost and risk-sharing mechanisms
advantageous to the employer. The
plans, in consequence, help ensure that each participating employer will
have access to a trained labor force whose members are able to move from
one employer and one job to another without
607 losing service credit toward pension benefits.
See 29 CFR § 2530.210(c)(1) (1991);
accord, Washington Star Co. v. International Typographical Union
Negotiated Pension Plan, 582 F.Supp. 301, 304 (DC1983).
Since the enactment of
ERISA in 1974, the Plan has been subject to the provisions of the statute
as a "defined benefit plan."
Such a plan is one that does not qualify as an " 'individual
account plan' or 'defined contribution plan,' " which provide, among
other things, for an individual account for each covered employee and for
benefits based solely upon the amount contributed to the covered
employee's account. See
29 U.S.C. §§ 1002(35), 1002(34), 1002(7).
Concrete Pipe has not challenged the determination that the Plan
falls within the statutory definition of defined benefit plan, and no
issue as to that is before the Court.
A
We have canvassed the history of ERISA and the MPPAA before.
See Pension Benefit Guaranty Corporation v. R.A. Gray & Co.,
supra; Connolly v. Pension
Benefit Guaranty Corporation, supra.
ERISA was designed "to ensure that employees and their
beneficiaries would not be deprived of anticipated retirement benefits by
the termination of pension plans before sufficient funds have been
accumulated in [them].... Congress
wanted to guarantee that if a worker has been promised a defined pension
benefit upon retirement -- and if he has fulfilled whatever conditions are
required to obtain a vested benefit -- he will actually receive it."
Id., 475 U.S., at 214, 106 S.Ct., at 1020 (citations and internal quotation marks omitted). As enacted in 1974, ERISA created the Pension Benefit
Guarantee Corporation (PBGC) to administer and enforce a pension plan
termination insurance program, to which contributors to both
single‑member and multiemployer plans were required to pay insurance
premiums. 29 U.S.C. §§
1302(a), 1306 (1988 ed. and Supp. III).
Under the terms of the statute as originally enacted, the guarantee
of basic 608 benefits by multiemployer plans that terminated was not to be
mandatory until 1978, and for terminations prior to that time, any
guarantee of benefits upon plan termination was discretionary with PBGC.
29 U.S.C. §§ 1381(c)(2)-(4) (1976 ed.).
If PBGC did choose to extend a guarantee when a multiemployer plan
terminated with insufficient assets to pay promised benefits, an employer
that had contributed to the plan in the five preceding years was liable to
PBGC for the shortfall in proportion to its share of contributions during
that 5-year period, up to 30 percent of the employer's net worth.
29 U.S.C. §§ 1362(b), 1364 (1976 ed.).
"In other words, any employer withdrawing from a multiemployer
plan was subject to a contingent liability that was dependent upon the
plan's termination in the next five years and the PBGC's decision to
exercise its discretion and pay guaranteed benefits."
Gray, 467 U.S., at 721, 104 S.Ct. at 2713.
"As the date for mandatory coverage of multiemployer
plans approached, Congress became concerned that a significant number of
plans were experiencing extreme financial hardship."
Ibid. Indeed, the
possibility of liability upon termination of a plan created an incentive
for employers to withdraw from weak multiemployer plans.
Connolly, 475 U.S., at 215, 106 S.Ct. at 1021. The consequent risk
to the insurance system was unacceptable to Congress, which in 1978
postponed the mandatory guarantee pending preparation by the PBGC of a
report "analyzing the problems of multiemployer plans and
recommending possible solutions."
Ibid. PBGC issued that
report on July 1, 1978. Pension
Benefit Guaranty Corporation, Multiemployer Study Required by P.L. 95-214
(1978). "To alleviate the problem of employer withdrawals, the
PBGC suggested new rules under which a withdrawing employer would be
required to pay whatever share of the plan's unfunded liabilities was
attributable to that employer's participation."
Connolly, 475 U.S., at 216, 106 S.Ct. at 1021 (citation and
internal quotation marks omitted).
609 Congress ultimately agreed, see id., at 217, 106 S.Ct. at 1022,
and passed the MPPAA, which was signed into law by the President on
September 26, 1980. Under
certain provisions of the MPPAA (which when enacted had an effective date
of April 29, 1980, 29 U.S.C. § 1461(e)(2)(A) (1976 ed., Supp. V)), if an
employer withdraws from a multiemployer plan, it incurs "withdrawal
liability" in the form of "a fixed and certain debt to the
pension plan." Gray, supra, 467 U.S., at 725, 104 S.Ct. at 2715.
An employer's withdrawal liability is its "proportionate share
of the plan's 'unfunded vested benefits,' " that is, "the
difference between the present value of vested benefits" (benefits
that are currently being paid to retirees and that will be paid in the
future to covered employees who have already completed some specified
period of service, 29 U.S.C. § 1053) "and the current value of the
plan's assets. 29 U.S.C. §§
1381, 1391." Gray,
supra, 467 U.S., at 725, 104 S.Ct. at 2715. [FN2]
FN2. In various places the
statute uses the terms "participant" and
"beneficiary," and these terms are defined at 29 U.S.C. §§
1002(7), 1002(8). For simplicity, we will use the term "covered
employee" to refer depending on context both to those earning service
credits and to those entitled to benefits.
B
The
MPPAA provides the procedure for calculating and assessing withdrawal
liability. The plan's actuary,
who is subject to regulatory and professional standards, 29 U.S.C. §§
1241, 1242; 26 U.S.C. §
7701(a)(35), must determine the present value of the plan's liability for
vested benefits. [FN3] In the
absence of regulations promulgated by the PBGC, the actuary must employ
"actuarial assumptions and methods which, in the aggregate, are
reasonable (taking into account the experience of the plan and reasonable
expectations) and which, in combination, offer the actuary's best estimate
of anticipated experience under the plan."
29 U.S.C. 610 §
1393(a)(1). [FN4] The
assumptions must cover such matters as mortality of covered employees,
likelihood of benefits vesting, and, importantly, future interest rates.
After settling the present value of vested benefits, the actuary
calculates the unfunded portion by deducting the value of the plan's
assets. § 1393(c).
FN3. Even if no
employer withdraws, ERISA requires an assessment of the plan's liability
at least annually. See
29 U.S.C. § 1082(c)(9) (1988 ed., Supp. III).
FN4.
While the PBGC is also authorized to promulgate regulations governing such
assumptions under 29 U.S.C. § 1393(a), it has not done so. See Brief for Pension Benefit Guaranty Corp. as Amicus
Curiae 7, n. 7.
In
order to determine a particular employer's withdrawal liability,
the unfunded vested liability is allocated under one of several
methods provided by law.
§ 1391. In
this case, the Plan used the presumptive method of § 1391(b),
which bases withdrawal liability on the proportion of total
employer contributions to the plan made by the withdrawing
employer during certain 5-year periods.
See §§ 1391(b)(2)(E)(ii), (b)(3)(B), (b)(4)(D)(ii).
In essence, the withdrawal liability imposes on the
withdrawing employer a share of the unfunded vested liability
proportional to the employer's share of contributions to the
plan during the years of its participation.
Withdrawal liability
is assessed in a notification by the "plan sponsor" (here the
trustees, see § 1301(a)(10)(A)) and a demand for payment.
§ 1399(b). The
statute requires notification and demand to be made "[a]s soon as
practicable after an employer's complete or partial withdrawal."
§ 1399(b)(1). A
"complete withdrawal"
"occurs when an
employer --
"(1) Permanently ceases to have an obligation to contribute under the
plan, or
"(2) permanently ceases all covered operations under the
plan." § 1383(a). [FN5]
FN5. There is an exception
to this definition that applies to the building and construction industry,
see § 1383(b), but neither party argues that it pertains in this case.
611
"[T]he date of a complete withdrawal is the date of the cessation of
the obligation to contribute or the cessation of covered operations."
§ 1383(e).
The
statute provides that if an employer objects after notice
and demand for withdrawal liability, and the parties cannot
resolve the dispute, § 1399(b)(2), it shall be referred to
arbitration. See
§ 1401(a)(1). Two
presumptions may attend the arbitration.
First, "any determination made by a plan sponsor
under [29 U.S.C. §§ 1381-1399 and 1405 (1988 ed. and Supp.
III) ] is presumed correct unless the party contesting the
determination shows by a preponderance of the evidence that
the determination was unreasonable or clearly erroneous."
29 U.S.C. § 1401(a)(3)(A).
Second, the sponsor's calculation of a plan's unfunded
vested benefits.
"is
presumed correct unless a party contesting the determination
shows by a preponderance of evidence that -- "(i)
the actuarial assumptions and methods used in the determination
were, in the aggregate, unreasonable (taking into account
the experience of the plan and reasonable expectations), or
"(ii)
the plan's actuary made a significant error in applying the
actuarial assumptions or methods."
§ 1401(a)(3)(B).
The statute provides for judicial
review of the arbitrator's decision by an action in the district
court to enforce, vacate, or modify the award. See § 1401(b)(2).
In any such action "there shall be a presumption,
rebuttable only by a clear preponderance of the evidence,
that the findings of fact made by the arbitrator were correct."
§ 1401(c).
II
The
parties to the Trust Agreement creating the Plan in 1962 are
the Southern California District Council of Laborers (Laborers)
and three associations of contractors, the
612 Building Industry of California, Inc., the Engineering
Contractors Association, and the Southern California Contractors
Association, Inc. App. 75, ¶ 6 (stipulation of facts filed
in the District Court).
Under § 302(c)(5)(B) of the Labor Management Relations
Act, 1947 (LMRA), 29 U.S.C. § 186(c)(5)(B), when a union participates
in management of a plan permitted by the LMRA, the plan must
be administered jointly by representatives of labor and management.
Accordingly, half of the Plan's trustees are selected
by the Laborers, and half by these contractors' associations.
Concrete Pipe has never been a member of any of the
contractors' associations that are parties to the Trust Agreement.
In
1976, Concrete Pipe, which is a wholly owned subsidiary of
Concrete Pipe and Products Co., Inc., purchased certain assets
of another company, Cen-Vi-Ro, including a concrete pipe manufacturing
plant near Shafter, California, which Concrete Pipe continued
to operate much as Cen-Vi-Ro had done. Cen-Vi- Ro had collective-bargaining
agreements with several unions including the Laborers, and
Concrete Pipe abided by the agreement with the latter by contributing
to the Plan at a specified rate for each hour worked by a
covered employee. [FN6]
In 1978, Concrete Pipe negotiated a new 3-year contract
with the Laborers that called for continuing contributions
to be made to the Plan based on hours worked by covered employees
in the collective-bargaining unit. [FN7]
The collective-bargaining agreement specified that
it would remain in effect until June 30, 1981, and thereafter
from year to year unless either Concrete Pipe or the Laborers
gave notice of a desire to renegotiate or terminate it.
" 'Such written notice [was to] be given at least
sixty (60) 613
days prior to June 30 ... [and if] no agreement [was] reached
by June 30 ... the Employer or the [Laborers might] thereafter
give written notice to the other that on a specified date
[at least] fifteen (15) days [thereafter] the Agreement [should]
be considered terminated.' "
App. 76.
FN6.
The average rate for covered employees at which Concrete Pipe
contributed to the Plan in 1977 was $1.14 per hour, and Concrete
Pipe's contributions for 1977 totaled $29,337.71.
FN7.
The collective-bargaining agreement provided for contributions
for each laborer at a rate of $1.20 per hour.
In 1978 Concrete Pipe's total contribution to the Plan
was $49,913.04, and in 1979 it was $20,826.60.
In
August 1979, Concrete Pipe stopped production at the Shafter
facility. Although
the details do not matter here, by October 1979, work by employees
covered by the agreement with the Laborers had virtually ceased,
and Concrete Pipe eventually stopped making contributions
to the Plan. In
the spring of 1981, Concrete Pipe and the Laborers each sent
the other a timely notice of a desire to renegotiate the collective-bargaining
agreement. Concrete
Pipe subsequently bargained to an impasse and, on November
30, 1981, sent the Laborers a letter withdrawing recognition
of that union as an employee representative, and giving notice
of intent to terminate the 1978 collective-bargaining agreement.
At about the same time, however, in November 1981,
Concrete Pipe reopened the Shafter plant to produce 7,000
tons of concrete pipe needed to fill two orders for which
it had successfully bid.
It hired employees in classifications covered by
its prior
agreement with the Laborers, but did not contribute to the
Plan for their work.
In
January 1982, the Plan notified Concrete Pipe of withdrawal
liability claimed to amount to $268,168.81.
See id., at 89-94.
Although the demand letter did not specify the date
on which the Plan contended that "complete withdrawal"
from it had taken place, it referred to the failure of Concrete
Pipe to make contributions to the Plan since February 1981,
and stated that "[w]e are further advised that you have
not signed a renewal of a collective bargaining agreement
obligating you to continue contributions to the Plan on behalf
of the Construction laborers currently in your employ."
Id., at 90.
The
Plan filed suit seeking the assessed withdrawal liability.
Concrete
Pipe countersued to bar collection, contending
614 that "complete withdrawal" had occurred
when operations at the Shafter plant ceased in August 1979,
a date prior to the effective date of the MPPAA, and challenging
the MPPAA on constitutional grounds.
These cases were consolidated in the United States
District Court for the Central District of California, which
sua sponte ordered the parties to arbitrate the issue of whether
withdrawal occurred prior to the effective date of the MPPAA.
[FN8]
FN8.
The District Court concluded that the effective date of the
withdrawal liability provisions of the MPPAA was September
26, 1980, in reliance on the Ninth Circuit's decision in Shelter
Framing Corp. v. Pension Benefit Guaranty Corporation, 705
F.2d 1502 (1983), which held the retroactivity provision of
the MPPAA unconstitutional.
App. 198.
The decision in Shelter Framing was reversed by this
Court in Pension Benefit Guaranty Corporation v. R.A. Gray
& Co., 467 U.S. 717, 104 S.Ct. 2709, 81 L.Ed.2d 601 (1984).
Subsequent to this Court's decision in Gray, Congress
amended the effective date of the MPAA's withdrawal liability
provisions. See
29 U.S.C. § 1461(e)(2)(A).
The
arbitration took place in two phases.
In the first, the arbitrator determined that Concrete
Pipe had not withdrawn from the Plan prior to the effective
date of the MPPAA.
App. 216.
In the second phase, explicitly applying the presumption
of 29 U.S.C. § 1401(a)(3)(B), the arbitrator found that Concrete
Pipe had failed to meet its burden of showing the actuarial
assumptions and methods to be unreasonable in the aggregate.
App. 400.
For reasons not at issue here, the arbitrator did rule
partially in Concrete Pipe's favor, and reduced the withdrawal
liability from $268,168.61 to $190,465.57.
Concrete
Pipe then filed a third action in the District Court, to set
aside or modify the arbitrator's decision, and again raised
its constitutional challenge.
Id., at 406.
The District Court treated Concrete Pipe's subsequent
motion for summary judgment as a petition to vacate the arbitrator's
award, which it denied, and granted a motion by the Plan to
confirm the award. Construction Laborers Pension Trust for
Southern California v. Cen-Vi-Ro Concrete Pipe
615 and Products, CV-82-5184-HLH (CD Cal., July 5, 1989),
App. 416-425. [FN9]
On Concrete Pipe's appeal, the judgment of the District
Court was affirmed.
Board of Trustees of Construction Laborers Pension
Trust for Southern California v. Concrete Pipe and Products
of California, Inc., 936 F.2d 576 (CA9 1991), App. 431-432,
judgt. order reported at 935 F.3d 576.
We granted certiorari limited to two questions presented,
which are set out in the margin.
504 U.S. 940, 112 S.Ct. 2273, 119 L.Ed.2d 200 (1992).
[FN10]
FN9. In
its motion to confirm the award, the Plan also asked that
it be modified.
The District Court treated this as a motion to vacate
the arbitration award and denied it as well.
See App. 416.
The Plan did not appeal.
FN10. Our
grant of certiorari was limited to the questions:
"Do the presumptions in 29 U.S.C. § 1401 favoring
multiemployer plans like Construction Laborers Pension Trust
for Southern California ... violate the due process rights
of Concrete Pipe and Products by denying access to an impartial
decisionmaker?"
and "Do the provisions of the Multi-Employer Pension
Plan Amendments Act ... violate the Fifth Amendment rights
of Concrete Pipe and Products, as applied, by retroactively
imposing withdrawal liability on an employer who never had
employees vested in the pension plan and whose collective
bargaining agreements specifically limited liability to contributions
made?" Pet.
for Cert. i.
III
Concrete
Pipe challenges the assessment of withdrawal liability on
several grounds, the first being that by placing determination
of withdrawal liability in the trustees, subject to the presumptions
provided by § 1401, the MPPAA is unconstitutional because
it denies Concrete Pipe an impartial adjudicator. This is
not the first time this legal question has been before the
Court. See Pension Benefit Guaranty Corporation v. Yahn &
McDonnell, Inc., 481 U.S. 735, 107 S.Ct. 2171, 95 L.Ed.2d
692 (1987), aff'g by an equally divided Court United Retail
& Wholesale Employees Teamsters Union Local No. 115 Pension
Plan v. Yahn & McDonnell, Inc., 787 F.2d 128 (CA3 1986).
616 A
1
Concrete
Pipe and its amici point to several potential sources of trustee
bias toward imposing the greatest possible withdrawal liability.
The one they emphasize most strongly has roots in the
fact that "all of the trustees, including those selected
by employers, are fiduciaries of the fund, 29 U.S.C. § 1002(21)(
[A] ), and thus owe an exclusive duty to the fund."
Id., at 139 (emphasis omitted).
As we said in another case discussing employee benefit
pension plans permitted under LMRA:
"Under
principles of equity, a trustee bears an unwavering duty of
complete loyalty to the beneficiary of the trust, to the exclusion
of the interests of all other parties.
To deter the trustee from all temptation and to prevent
any possible injury to the beneficiary, the rule against a
trustee dividing his loyalties must be enforced with 'uncompromising
rigidity.' .
.
.
.
.
"In
sum, the duty of the management-appointed trustee of an employee
benefit fund under § 302(c)(5) is directly antithetical to
that of an agent of the appointing party....
ERISA essentially codified the strict fiduciary standards
that a § 302(c)(5) trustee must meet.
[Title 29 U.S.C. § 1104(a)(1) ] requires a trustee
to 'discharge his duties ... solely in the interest of the
participants [i.e., covered employees] and beneficiaries.'
" NLRB v. Amax Coal Co.,
453 U.S. 322, 329-332, 101 S.Ct. 2789, 2794-2795, 69 L.Ed.2d
672 (1981) (citations and footnote omitted).
The resulting tug away
from the interest of the employer is fueled by the threat
of personal liability for any breach of the trustees' fiduciary
responsibilities, obligations, or duties, 29 U.S.C. § 1109,
which may be enforced by civil actions brought by the Secretary
of Labor or any covered employee or beneficiary of the plan,
§ 1132(a)(2).
617 The trustees could act in a
biased fashion for several reasons.
The most obvious would be in attempting to maximize
assets available for the beneficiaries of the trust by making
findings to enhance withdrawal liability. The next would not
be so selfless, for if existing underfunding was the consequence
of prior decisions of the trustees, those decisions could,
if not offset, leave the trustees open to personal liability.
See Brief for American Trucking Associations, Inc.,
as Amicus Curiae 9.
A risk of bias may also inhere in the mere fact that,
fiduciary obligations aside, the trustees are appointed by
the unions and by employers.
Union trustees may be thought to have incentives, unrelated
to the question of withdrawal, to impose greater rather than
lesser withdrawal liability.
Employer trustees may be responsive to concerns of
those employers who continue to contribute, whose future burdens
may be reduced by high withdrawal liability, and whose competitive
position may be enhanced to boot.
See Brief for Midwest Motor Express, Inc., et al. as
Amici Curiae 8, citing Note, Trading Fairness for Efficiency:
Constitutionality of the Dispute Resolution Procedures of
the Multiemployer Pension Plan Amendments Act of 1980, 71
Geo.L.J. 161, 168 (1982).
As against these supposed threats
to the trustees' neutrality, due process requires a "neutral
and detached judge in the first instance," Ward v. Village
of Monroeville, 409 U.S. 57, 61-62, 93 S.Ct. 80, 84, 34 L.Ed.2d
267 (1972), and the command is no different when a legislature
delegates adjudicative functions to a private party, see Schweiker
v. McClure, 456 U.S. 188, 195, 102 S.Ct. 1665, 1669, 72 L.Ed.2d
1 (1982). "That
officers acting in a judicial or quasi-judicial capacity are
disqualified by their interest in the controversy to be decided
is, of course, the general rule." Tumey v. Ohio, 273 U.S.
510, 522, 47 S.Ct. 437, 441, 71 L.Ed. 749 (1927).
Before one may be deprived of a protected interest,
whether in a criminal or civil setting, see Marshall v. Jerrico,
Inc., 446 U.S. 238, 242, and n. 2, 100 S.Ct. 1610, 1613, and
n. 2, 64 L.Ed.2d 182 (1980), one is entitled as a matter of
due process of law to an adjudicator who is not in a situation
" 'which would offer a possible
618
temptation to the average man as a judge
... which might lead him not to hold the balance nice, clear
and true....' "
Ward, supra, 409 U.S. at 60, 93 S.Ct. at 81 (quoting
Tumey, supra, 273 U.S., at 532, 47 S.Ct., at 444).
Even appeal and a trial de novo will not cure a failure
to provide a neutral and detached adjudicator.
409 U.S., at 61, 93 S.Ct. at 83.
"[J]ustice," indeed,
"must satisfy the appearance of justice, and this stringent
rule may sometimes bar trial [even] by judges who have no
actual bias and who would do their very best to weigh the
scales of justice equally between contending parties."
Marshall v. Jerrico, Inc., supra, 446 U.S., at 243,
100 S.Ct., at 1613 (citations and internal quotation marks
omitted). This,
too, is no less true where a private party is given statutory
authority to adjudicate a dispute, and we will assume that
the possibility of bias, if only that stemming from the trustees'
statutory role and fiduciary obligation, would suffice to
bar the trustees from serving as adjudicators of Concrete
Pipe's withdrawal liability.
2
The assumption does not win the
case for Concrete Pipe, however, for a further strand of governing
law has to be applied.
Not all determinations affecting liability are adjudicative,
and the " 'rigid requirements' ... designed for officials
performing judicial or quasi-judicial functions, are not applicable
to those acting in a prosecutorial or plaintiff-like capacity."
446 U.S., at 248, 100 S.Ct., at 1616.
Where an initial determination is made by a party acting
in an enforcement capacity, due process may be satisfied by
providing for a neutral adjudicator to "conduct a de
novo review of all factual and legal issues."
Cf. id., at 245, 100 S.Ct., at 1614;
see also id., at 247‑248, and n. 9, 100 S.Ct.,
at 1615 and n. 9; cf.
Withrow v. Larkin, 421 U.S. 35, 58, 95 S.Ct. 1456, 1470, 43
L.Ed.2d 712 (1975) ("Clearly, if the initial view of
the facts based on the evidence derived from nonadversarial
processes as a practical or legal matter foreclosed fair and
effective consideration at a subsequent adversary hearing
leading to ultimate decision, a substantial due process question
would be raised").
619 The
distinction between adjudication and enforcement disposes
of the claim that the assumed bias or appearance of bias in
the trustees' initial determination of withdrawal liability
alone violates the Due Process Clause, much as it did the
similar claim in Marshall v. Jerrico.
Although we were faced there with a federal agency
administrator who determined violations of a child labor law
and assessed penalties under the statute, we concluded that
the administrator could not be held to the high standards
required of those "whose duty it is to make the final
decision and whose impartiality serves as the ultimate guarantee
of a fair and meaningful proceeding in our constitutional
regime." 446
U.S., at 250, 100 S.Ct. at 1617.
Of the administrator there we said, "He is not
a judge. He
performs no judicial or quasi-judicial functions.
He hears no witnesses and rules on no disputed factual
or legal questions.
The function of assessing a violation is akin to that
of a prosecutor or civil plaintiff." Id., at 247, 100
S.Ct., at 1615.
This
analysis applies with equal force to the trustees, who, we
find, act only in an enforcement capacity.
The statute requires the plan sponsor, here the trustees,
to notify the employer of the amount of withdrawal liability
and to demand payment, 29 U.S.C. § 1399(b)(1), actions that
bear the hallmarks of an assessment, not an adjudication.
The trustees are not required to hold a hearing, to
examine witnesses, or to adjudicate the disputes of contending
parties on matters of fact or law. [FN11]
In Marshall, we observed that an employer "except[ing]
to a penalty ... is entitled to a de novo hearing before an
administrative law judge," 446 U.S., at 247, 100 S.Ct.,
at 1615, and we concluded that this latter proceeding was
the 620 "initial
adjudication," id., at 247, n. 9, 100 S.Ct., at 1615,
n. 9. Likewise
here, we conclude that the first adjudication is the proceeding
that occurs before the arbitrator, not the trustees' initial
determination of liability. [FN12]
FN11.
While the employer "may ask the plan sponsor to review
any specific matter relating to the determination of the employer's
liability and the schedule of payments," 29 U.S.C. §
1399(b)(2), and while the plan sponsor must then respond,
ibid., this hardly amounts to "adjudication." The statute does
not require the employer to exhaust the avenue of making a
request of the plan sponsor prior to initiating arbitration
proceedings. See
§ 1401(a)(1).
FN12.
"[W]e need not say with precision what limits there may
be on a financial or personal interest of one who performs
a prosecutorial function," Marshall, 446 U.S., at 250,
100 S.Ct., at 1617 (footnote omitted), as that issue is not
within the scope of the questions on which we granted certiorari
in this case.
B
This
does not end our inquiry, however, for Concrete Pipe goes
on to argue that the statutory presumptions preserve the trustees'
bias by limiting the arbitrator's autonomy to determine withdrawal
liability, and thereby work to deny the employer a fair adjudication.
1
Under
the first provision at issue here, "any determination
made by the plan sponsor under [29 U.S.C. §§ 1381-1399 and
1405] is presumed correct unless the party contesting the
determination shows by a preponderance of the evidence that
the determination was unreasonable or clearly erroneous."
29 U.S.C. § 1401(a)(3)(A).
Concrete Pipe argues that this presumption denied it
an impartial adjudicator on the issue of its withdrawal date,
thus raising a constitutional question on which the Courts
of Appeals have divided. [FN13]
FN13.
The Courts of Appeals for the First, Second, Fourth, Ninth,
and District of Columbia Circuits have found the provision
at issue constitutional, while the Court of Appeals for the
Third Circuit has struck it down.
Compare Keith Fulton & Sons, Inc. v. New England
Teamsters and Trucking Indus. Pension Fund, Inc., 762 F.2d
1137, 1140-1143 (CA1 1985) (en banc);
Board of Trustees of Western Conference of Teamsters
Pension Trust Fund v. Thompson Bldg. Materials, Inc., 749
F.2d 1396, 1403-1404 (CA9 1984), cert. denied, 471 U.S. 1054,
105 S.Ct. 2116, 85 L.Ed.2d 481 (1985); Washington Star Co. v.
International Typographical Union Negotiated Pension Plan,
235 U.S.App.D.C. 1, 10, 729 F.2d 1502, 1511 (1984);
Textile Workers Pension Fund v. Standard Dye &
Finishing Co., 725 F.2d 843, 855 (CA2), cert. denied sub nom.
Sibley, Lindsay & Curr Co. v. Bakery, Confectionery &
Tobacco Workers, 467 U.S. 1259, 104 S.Ct. 3554, 82 L.Ed.2d
856 (1984); and
Republic Indus., Inc. v. Teamsters Joint Council No. 83 of
Virginia Pension Fund, 718 F.2d 628, 639-641 (CA4 1983), cert.
denied, 467 U.S. 1259, 104 S.Ct. 3553, 82 L.Ed.2d 855 (1984),
with United Retail & Wholesale Employees Teamsters Union
Local No. 115 Pension Plan v. Yahn & McDonnell, Inc.,
787 F.2d 128, 138-142 (CA3 1986), aff'd by an equally divided
Court sub nom. Pension Benefit Guaranty Corporation v. Yahn
& McDonnell, Inc., 481 U.S. 735, 107 S.Ct. 2171, 95 L.Ed.2d
692 (1987).
621 The parties
apparently agree that this presumption applies only to factual
determinations, see Reply Brief for Petitioner 17;
Brief for Respondent 24 (deferring to brief for the
PBGC as amicus curiae );
Brief for Pension Benefit Guaranty Corporation as Amicus
Curiae 10, and n. 11, and this position is consistent with
a PBGC regulation requiring the arbitrator "[i]n reaching
his decision [to] follow applicable law, as embodied in statutes,
regulations, court decisions, interpretations of the agencies
charged with the enforcement of the Act, and other pertinent
authorities," 29 CFR § 2641.4(a)(1) (1992).
We will assume for purposes of this case that the regulation
reflects a sound reading of the statute. [FN14]
FN14. There
is no utility in attempting to construe § 1401(a)(3)(A) finely
to apply the "unreasonable" standard to certain
determinations possible under §§ 1381-1399 and 1405, and the
"clearly erroneous" formulation to others.
These distinctions are not relevant in light of the
relationship in this context of both of these terms to the
statutory phrase requiring a showing "by a preponderance,"
which we explain below.
a
It is clear that the presumption
favoring determinations of the plan sponsor shifts a burden
of proof or persuasion to the employer.
The hard question is what the employer must show under
the statute to rebut the plan sponsor's factual determinations,
that is, how and to what degree of probability the employer
must persuade the arbitrator that the sponsor was wrong.
The question is hard because the statutory text refers
to three different concepts in identifying this burden:
"preponderance," "clearly erroneous,"
and "unreasonable."
622 The burden of showing something
by a "preponderance of
the evidence," the most common standard in the civil
law, "simply requires the trier of fact 'to believe that
the existence of a fact is more probable than its nonexistence
before [he] may find in favor of the party who has the burden
to persuade the [judge] of the fact's existence.' "
In re Winship, 397 U.S. 358, 371-372, 90 S.Ct. 1068,
1076, 25 L.Ed.2d 368 (1970) (Harlan, J., concurring) (brackets
in original) (citation omitted).
"A finding is 'clearly erroneous' when although
there is evidence to support it, the reviewing [body] on the
entire evidence is left with the definite and firm conviction
that a mistake has been committed."
United States v. United States Gypsum Co., 333 U.S.
364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746 (1948). A showing
of "unreasonableness" would require even greater
certainty of error on the part of a reviewing body. See, e.g., Anderson
v. Liberty Lobby, Inc., 477 U.S. 242, 252, 106 S.Ct. 2505,
2512, 91 L.Ed.2d 202 (1986).
In creating the presumption
at issue, these terms are combined in a very strange way.
As our descriptions indicate, the first, "preponderance,"
is customarily used to prescribe one possible burden or standard
of proof before a trier of fact in the first instance, as
when the proponent of a proposition loses unless he proves
a contested proposition by a preponderance of the evidence.
The term thus belongs in the same category with "clear
and convincing" and "beyond a reasonable doubt,"
which are also used to prescribe standards of proof (but when
greater degrees of certainty are thought necessary).
Before any such burden can be satisfied in the first
instance, the factfinder must evaluate the raw evidence, finding
it to be sufficiently reliable and sufficiently probative
to demonstrate the truth of the asserted proposition with
the requisite degree of certainty.
The second and third terms differ
from the first in an important way. They are customarily used
to describe, not a degree of certainty that some fact has
been proven in the first instance, but a degree of certainty
that a factfinder in the first instance made a mistake in
concluding that a fact
623 had been proven under the applicable
standard of proof.
They are, in other words, standards of review, and
they are normally applied by reviewing courts to determinations
of fact made at trial by courts that have made those determinations
in an adjudicatory capacity (unlike the trustees here).
See, e.g., Fed.Rule Civ.Proc. 52(a).
As the terms readily indicate, a reviewing body characteristically
examines prior findings in such a way as to give the original
factfinder's conclusions of fact some degree of deference.
This makes sense because in many circumstances the
costs of providing for duplicative proceedings are thought
to outweigh the benefits (the second would render the first
ultimately useless), and because, in the usual case, the factfinder
is in a better position to make judgments about the reliability
of some forms of evidence than a reviewing body acting solely
on the basis of a written record of that evidence.
Evaluation of the credibility of a live witness is
the most obvious example.
Thus, review under the "clearly
erroneous" standard is significantly deferential, requiring
a "definite and firm conviction that a mistake has been
committed."
And application of a reasonableness standard is even
more deferential than that, requiring the reviewer to sustain
a finding of fact unless it is so unlikely that no reasonable
person would find it to be true, to whatever the required
degree of proof.
The strangeness in the statutory
language creating the first presumption arises from the combination
of terms from the first category (burdens of proof) with those
from the second (standards of review).
It is true, of course, that this apparent confusion
of categories may have resulted from the hybrid nature of
the arbitrator's proceeding in which it is supposed to be
applied. The
arbitrator here does not function simply as a reviewing body
in the classic sense, for he is not only obliged to enquire
into the soundness of the sponsor's determinations when they
are challenged, but may receive new evidence in the course
of his review and adopt his own conclusions of fact.
He may conduct proceedings in the
624
same manner and with the same powers
as an arbitrator may do under Title 9 of the United State
Code, see 29 U.S.C. § 1401(b)(3), being authorized, for example,
to hear (indeed to subpoena) witnesses and to take evidence.
See 9 U.S.C. § 7; 29 U.S.C. § 1401(b)(3)
(making specific reference to subpoena power).
He is, then, a reviewing body (as is clear from his
obligation, absent a contrary showing, to deem certain determinations
by the plan sponsor correct), but a reviewing body invested
with the further powers of a finder of fact (as is clear from
his power to take evidence in the course of his review and
from the presumption of correctness that a district court
is bound to give his "findings of fact," § 1401(c)).
The arbitrator may thus provide a dual sort of trial
and review, ultimately empowered to draw his own conclusions,
and it would make sense to describe his different functions
respectively by the language of trial and the language of
review.
It
does not, however, make sense to use the language of trial
and the language of review as the statute does, for the statute
does not refer to different arbitrator's functions in language
appropriate to each;
it refers, rather, to one single conclusion that must
be drawn about a determination previously made by a plan sponsor. By its terms the
statute purports to provide a standard for reviewing the sponsor's
findings, and it defines the nature of the conclusion the
arbitrator must draw by using a combination of terms that
are categorically ill-matched.
They are also inconsistent with each other on any reading.
As used here, as distinct from its more usual context,
the statutory phrase authorizing the arbitrator to reject
a factual conclusion upon proof by a "preponderance"
implies review of the sponsor's determination on the basis
of the record, supplemented by any new evidence, for simple
error. If
this statutory phrase were given effect, and the arbitrator
concluded from a review of the record and of new evidence
that a finding of fact was more probably wrong than not, it
would be rejected, and a different
625 finding might be substituted.
On the other hand, requiring a showing that the sponsor's
determination was "clearly erroneous" or "unreasonable"
would grant the plan sponsor's factual findings a great deal
of deference.
But to say in this context that one must demonstrate
that something is more probably clearly erroneous than not
or more probably than not unreasonable is meaningless.
One might as intelligibly say, in a trial court, that
a criminal prosecutor is bound to prove each element probably
true beyond a reasonable doubt. The statute is thus incoherent
with respect to the degree of probability of error required
of the employer to overcome a factual conclusion made by the
plan sponsor. [FN15]
FN15. Justice
THOMAS reads the statute not to be about the standard of review
of the plan sponsor's findings of fact at all.
On his reading, "clearly erroneous" is not
a term of art, but an attempt at independent literal description.
Under his reading, if the arbitrator concludes a factual
determination of a plan sponsor is probably wrong, it will
nonetheless be permitted to stand, unless the error is "obvious,
plain, gross, significant, or manifest."
See post, at 2295 (citation omitted). Justice THOMAS
does not adequately explain what purpose would be served by
a statute that let some erroneous (and presumably material)
factual determinations stand even when they were "clearly
erroneous" in the legal sense or "unreasonable,"
merely because of the degree to which they happened to deviate
from the true facts, even when the latter are supported by
overwhelming evidence.
He does refer to a possible congressional desire to
avoid disputes over "insignificant errors," post,
at 2296, but under his reading a factual error could be significant,
in the sense that it was both material and undeniably incorrect,
and yet still stand because it was not that far different
from the truth. Justice THOMAS cites the presumption of innocence
for the proposition that the presumption at issue here does
not imply a standard of review.
See post, at 2295.
But just because some presumptions do not imply standards
of review does not mean that this one does not.
Here, by its terms, the statutory presumption says
that factual findings of the plan sponsor will stand unless
some showing is made, necessarily implying a standard of review
of those findings.
The proper response to this incomprehensibility
is obviously important in deciding this case.
If it permitted an employer to rebut the plan sponsor's
factual conclusions by a
626
preponderance, merely placing a burden
of persuasion on the employer, and permitting adjudication
of the facts by the arbitrator without affording deference
to the plan sponsor's determinations, the provision would
be constitutionally unremarkable.
For although we have observed that "[w]here the
burden of proof lies on a given issue is, of course, rarely
without consequence and frequently may be dispositive to the
outcome of the litigation or application, ... [o]utside the
criminal law area, where special concerns attend, the locus
of the burden of persuasion is normally not an issue of federal
constitutional moment." Lavine v. Milne, 424 U.S. 577,
585, 96 S.Ct. 1010, 1016, 47 L.Ed.2d 249 (1976) (footnote
omitted). Concrete
Pipe points to no special interest that would distinguish
this from the normal case.
It is indeed entirely sensible to burden the party
more likely to have information relevant to the facts about
its withdrawal from the Plan with the obligation to demonstrate
that facts treated by the Plan as amounting to a withdrawal
did not occur as alleged. Such was the rule at common law.
W. Bailey, Onus Probandi 1 (1886) (citing Powell on
Evidence 167‑171) ("In every case the onus probandi
lies on the party who wishes to support his case by a particular
fact which lies more peculiarly within his knowledge, or of
which he is supposed to be cognizant").
On
the other hand, if the employer were required to show the
trustees' findings to be either "unreasonable or clearly
erroneous," there would be a substantial question of
procedural fairness under the Due Process Clause.
In essence, the arbitrator provided for by the statute
would be required to accept the plan sponsor's findings, even
if they were probably incorrect, absent a showing at least
sufficient to instill a definite or firm conviction that a
mistake had been made.
Cf. Withrow v. Larkin, 421 U.S., at 58, 95 S.Ct., at
1470. In
light of our assumption of possible bias, the employer would
seem to be deprived thereby of the impartial adjudication
in the first instance to which it is entitled under the Due
Process Clause.
See supra, at 2276-2277.
627 b
Having
found the statutory language itself incoherent, we turn, as
we would in the usual case of textual ambiguity, to the legislative
purpose as revealed by the history of the statute, for
such light as it may shed. [FN16]
Unsurprisingly, we have found no direct discussion
in the legislative history of the degree of certainty on the
part of the arbitrator required for the employer to overcome
the sponsor's factual conclusions.
The Report of the House Committee on Education and
Labor on the bill that became the MPPAA describes the presumption
as applying to "a determination of withdrawal liability
by a plan," and lumps it together with the statutory
presumption, discussed below, that applies to the choice of
actuarial assumptions and methods.
See H.R.Rep. No. 96-869, pt. 1, p. 86 (1980);
29 U.S.C. § 1401(a)(3)(B). [FN17]
The Report states that
FN16. The
textual incomprehensibility concerns a very narrow matter,
and we find nothing in the structure of the statutory scheme
that provides elucidation.
FN17. The
presumption at issue here was included in a new § 4221 added
by the MPPAA to ERISA.
In the text of the version of the bill to which the
House Report refers the presumption was contained in § 4203,
and the provision began:
"For purposes of this part, a determination made
with respect to a plan under section 4201 [relating to employer
withdrawals] is presumed correct unless the party contesting
the determination shows...." See H.R.Rep. No. 96‑869,
pt. 1, p. 17 (1980), 1980 U.S.C.C.A.N. p. 2918.
As enacted, this text was replaced with "For purposes
of any proceeding under this section, any determination made
by a plan sponsor under sections 4201 through 4219 and section
4225 is presumed correct unless the party contesting the determination
shows...." Pub.L.
93-406, title IV, § 4221, as added, Pub.L. 96-364, title I
§ 104(2), Sept. 26, 1980, 94 Stat. 1239, 29 U.S.C. § 1401(a)(3)(A).
The text of what was called § 4201 differs somewhat
from the text of the sections to which the enacted bill refers,
which are now codified at 29 U.S.C. §§ 1381-1399 and 1405.
Our concern with legislative history here goes only
to the question of what degree of certainty of error Congress
intended to require in this situation. While the change
in referent that took place might have some implications for
this question, we do not think anything relevant in the legislative
history turns on the different scope of the earlier version
of the bill.
628
"[t]hese rules are necessary in
order to ensure the enforceability of employer liability.
In the absence of these presumptions, employers could
effectively nullify their obligation by refusing to pay and
forcing the plan sponsor to prove every element involved in
making an actuarial determination. The committee believes
it is extremely important that a withdrawn employer begin
making the annual payments even though the period of years
for which payments must continue will be based on the actual
liability allocated to the employer."
H.R.Rep. 96-869, pt. 1, supra, at 86, 1980 U.S.C.C.A.N.
at 2954.
The only other comment that we
have found in the legislative history occurs in a Report prepared
by the Senate Committee on Labor and Human Resources, which
first purports to speak about both statutory presumptions,
but directs its brief discussion to problems unique to "technical
actuarial matters."
See S. 1076:
The Multiemployer Pension Plan Amendments Act of 1980:
Summary and Analysis of Consideration, 96th Cong.,
2d Sess., 20‑21 (Comm.Print 1980) (hereinafter Committee
Print); see also
infra, at 2286, and n. 20.
The
legislative history thus sheds little light on the odd language
chosen to describe the employer's burden. All it tells us is
that the provision's purpose is to prevent the employer from
"forcing the plan sponsor to prove every element involved
in making an actuarial determination." Since this purpose
would be served simply by placing the burden of proof as to
historical fact on the employer, however light or heavy that
burden may be, the legislative history does nothing to make
sense of the drafter's failure to choose among the standards
included in the text.
c
The
only way out of the muddle is by a different rule of construction.
It is a hoary one that, in a case of statutory ambiguity,
"where an otherwise acceptable construction of
629 a statute would raise serious
constitutional problems,
the Court will construe the statute to avoid such problems
unless such construction is plainly contrary to the intent
of Congress." Edward
J. DeBartolo Corp. v. Florida Gulf Coast Building & Construction
Trades Council, 485 U.S. 568, 575, 108 S.Ct. 1392, 1397, 99
L.Ed.2d 645 (1988).
"Federal statutes are to be so construed as to
avoid serious doubt of their constitutionality.
'When the validity of an act of Congress is drawn in
question, and even if a serious doubt of constitutionality
is raised, it is a cardinal principle that this Court will
first ascertain whether a construction of the statute is fairly
possible by which the question may be avoided.'
Crowell v. Benson, 285 U.S. 22, 62 [52 S.Ct. 285, 296,
76 L.Ed. 598 (1932) ]."
Machinists v. Street, 367 U.S. 740, 749-750, 81 S.Ct.
1784, 1790, 6 L.Ed.2d 1141 (1961).
Cf. Parsons v. Bedford, 28 U.S. (3 Pet.) 433, 448-449,
7 L.Ed. 732 (1830) (Story, J.) (a construction that would
render a statute unconstitutional should be avoided); Murray
v. Schooner Charming Betsy, 6 U.S. (2 Cranch) 64, 118, 2 L.Ed.
208 (1804) (Marshall, C.J.).
Although we are faced here not
with ambiguity within the usual degree, but with incoherence,
we have a common obligation in each situation to resolve the
uncertainty in favor of definite meaning, and the canon for
resolving ambiguity applies with equal force when terminology
renders a statute incoherent.
In applying that canon here, we must give effect to
the one conclusion clearly supported by the statutory language,
that Congress intended to shift the burden of persuasion to
the employer in a dispute over a sponsor's factual determination.
This objective can be realized without raising serious
constitutional concerns simply by construing the presumption
to place the burden on the employer to disprove a challenged
factual determination by a preponderance.
In so construing the statute we make no pretense to
have read the congressional mind to perfection.
We would not, indeed, even have this problem if an
argument could not obviously be made that Congress intended
greater deference than the preponderance standard extends.
But one could hardly call the intent clear after wondering
why the preponderance
630 standard was also included.
In these circumstances it is enough that the choice
to attain coherence by obviating constitutional problems is
not "plainly contrary to the intent of Congress."
DeBartolo, supra, 485 U.S., at 575, 108 S.Ct., at 1397.
Because
the statute as we construe it does not foreclose any factual
issue from independent consideration by the arbitrator (the
presumption is, again, assumed by all to be inapplicable to
issues of law), there is no constitutional infirmity in it.
For the same reason, that an employer may avail itself
of independent review by the concededly neutral arbitrator,
we find no derivative constitutional defect infecting the
further presumption that a district court must afford to an
arbitrator's findings of fact.
See 29 U.S.C. § 1401(c).
d
Before applying the presumption
to this case, one must recognize that in spite of Concrete
Pipe's contention to the contrary, determining the date of
"complete withdrawal" presents not a mere question
of fact on which the arbitrator was required in the first
instance to apply the § 1401(a)(3)(A) presumption, but a mixed
question of fact and law. The relevant facts
are about the closure of the Shafter plant (such as the intent
of Concrete Pipe with respect to the plant, its expression
of that intent, its activities while the plant was not operating,
and the circumstances of the plant's reopening), while the
question whether these facts amount to a "complete withdrawal"
is one of law.
As
to the truly factual issues, the arbitrator's decision fails
to reveal the force with which factual conclusions by the
trustees here were presumed correct, and in such a case we
would ordinarily reverse the judgment below for consideration
of the extent to which the arbitrator's application of the
presumption was
contrary to the construction we adopt
today. But
two reasons (urged upon us by neither party) persuade us not
to take this course:
the Plan's letter to Concrete Pipe contains no statement
of facts justifying the trustees'
631 demand, and the parties entered
into a factual stipulation in the District Court prior to
commencing the arbitration. Because of these two circumstances,
there were virtually no contested factual determinations to
which the arbitrator might have deferred.
And, on the one question of fact that may have been
disputed, the arbitrator found, apparently in the first instance,
that Concrete Pipe's intent in closing the Shafter plant had
been to cease operations permanently.
App. 213-214. [FN18]
FN18.
Despite this favorable finding, Concrete Pipe still lost,
of course. The
arbitrator treated subjective intent as irrelevant.
See App. 213-215. While the District
Court and the Court of Appeals, which relied on the District
Court's reasoning, did not go so far, see id., at 419-420,
any factual deference in their decisions would be to the arbitrator's
finding, itself untainted by the force of any presumption.
See 29 U.S.C. § 1401(c);
Fed.Rule Civ.Proc. 52(a).
While
we express no opinion on whether the facts in this case constitute
a "complete
withdrawal" within the meaning of the statute, a question
not before us today, the approach taken by the arbitrator
and the courts below is not inconsistent with our interpretation
of the first presumption.
The determination of the date of withdrawal by the
arbitrator did not involve a misapplication of the statutory
presumption, and it did not deprive Concrete Pipe of its right
to procedural due process.
2
The
second presumption at issue attends the calculation of the
amount of withdrawal liability.
The statute provides that in the absence of more particular
PBGC regulations, the plan is required to use "actuarial
assumptions and methods which, in the aggregate, are reasonable
(taking into account the experience of the plan and reasonable
expectations) and which, in combination, offer the actuary's
best estimate of anticipated experience under the plan."
29 U.S.C. § 1393(a)(1).
The presumption in question arises under § 1401(a)(3)(B),
which provides that
632
"the
determination of a plan's unfunded vested benefits for a plan
year, [is] presumed correct unless a party contesting the
determination shows by a preponderance of evidence that --
"(i)
the actuarial assumptions and methods used in the determination
were, in the aggregate, unreasonable (taking into account
the experience of the plan and reasonable expectations), or
"(ii)
the plan's actuary made a significant error in applying the
actuarial assumptions or methods."
Concrete Pipe's concern is with
the presumptive force of the actuarial assumptions and methods
covered by subsection (i).
While this provision is like
its counterpart creating the presumption as to factual determinations
in placing the burden of proof on the employer, the issues
implicated in applying it to the actuary's work are not the
same. As the text plainly indicates, the assumptions and methods
used in calculating withdrawal liability are selected in the
first instance not by the trustees, but by the plan actuary.
For a variety of reasons, this actuary is not, like
the trustees, vulnerable to suggestions of bias or its appearance.
Although plan sponsors employ them, actuaries are trained
professionals subject to regulatory standards.
See 29 U.S.C. §§ 1241, 1242;
26 U.S.C. § 7701(a)(35).
The technical nature of an actuary's assumptions and
methods, and the necessity for applying the same assumptions
and methods in more than one context, as a practical matter
limit the opportunity an actuary might otherwise have to act
unfairly toward the withdrawing employer.
The statutory requirement (of "actuarial assumptions
and methods -- which, in the aggregate, are reasonable ...")
is not unique to the withdrawal liability context, for the
statute employs
identical language in 29 U.S.C. § 1082(c)(3) to describe the
actuarial assumptions and methods to be used in determining
whether a plan has satisfied the minimum funding requirements
contained in the statute.
The use of the same language to describe the actuarial
assumptions 633
and methods to be used in these different
contexts tends to check the actuary's discretion in each of
them.
"Using
different assumptions [for different purposes] could very
well be attacked as presumptively unreasonable both in arbitration
and on judicial review.
"[This]
view that the trustees are required to act in a reasonably
consistent manner greatly limits their discretion, because
the use of assumptions overly favorable to the fund in one
context will tend to have offsetting unfavorable consequences
in other contexts.
For example, the use of assumptions (such as low interest
rates) that would tend to increase the fund's unfunded vested
liability for withdrawal liability purposes would also make
it more difficult for the plan to meet the minimum funding
requirements of § 1082."
United Retail & Wholesale Employees Teamsters Union
Local No. 115 Pension Plan v. Yahn & McDonnell, Inc.,
787 F.2d, at 146-147 (Seitz, J., dissenting in part).
This point is not significantly
blunted by the fact that the assumptions used by the Plan
in its other calculations may be "supplemented by several
actuarial assumptions unique to withdrawal liability."
Brief for Respondent 26.
Concrete Pipe has not shown that any method or assumption
unique to the calculation of withdrawal liability is so manipulable
as to create a significant opportunity for bias to operate,
and arguably the most important assumption (in fact, the only
actuarial assumption or method that Concrete Pipe attacks
in terms, see Reply Brief for Petitioner 18-20) is the critical
interest rate assumption that must be used for other purposes
as well. [FN19]
FN19.
It may be that the trustees could, in theory, replace the
actuary's assumptions with their own, but that would involve
a different case from this, and while we are aware of at least
one case in which a plan sponsor exercised decisive influence
over an actuary whose initial assumptions it disliked, see
Huber v. Casablanca Industries, Inc., 916 F.2d 85, 93 (CA3
1990), we know of none in which a plan sponsor was found to
have replaced an actuary's actuarial methods or assumptions
with different ones of its own.
Although we express no view on the question whether
a plan sponsor must adopt the assumptions used by the actuary,
we note that the legislative history of § 1082, which was
enacted as part of ERISA in 1974, suggests that the acturarial
assumptions must be "independently determined by an actuary,"
and that it is "inappropriate for an employer to substitute
his judgment ... for that of a qualified actuary" with
respect to these assumptions. S.Rep. No. 93-383,
p. 70 (1973); see also H.R.Rep. No. 93-807,
p. 95 (1974), 1974 U.S.C.C.A.N. 4639, 4954, 4761.
634
The second major difference attending
the two presumptions lies in the sense of reasonableness that
must be disproven by an employer attacking the actuary's methods
and assumptions, as against the reasonableness of the trustees'
determinations of historical fact.
Following the usual presumption of statutory interpretation,
that the same term carries the same meaning whenever it appears
in the same Act, see Atlantic Cleaners & Dyers, Inc. v.
United States, 286 U.S. 427, 433, 52 S.Ct. 607, 608, 76 L.Ed.
1204 (1932), we might expect "reasonable" in § 1401(a)(3)(B)
to function here just as it did in § 1401(a)(3)(A), to denote
a certain range of probability that a factual determination
is correct. For
several reasons, however, we think it clear that this second
presumption of reasonableness functions quite differently.
First, of course, the statute
does not speak in terms of disproving the reasonableness of
the calculation of the employer's share of the unfunded liability,
which would be the finding of future fact most obviously analogous
to the findings of historical fact to which the § 1401(a)(3)(A)
presumption applies.
Section 1401(a)(3)(B) speaks instead of the aggregate
reasonableness of the assumptions
and methods employed by the actuary in calculating the
dollar liability figure.
Because a "method" is not "accurate"
or probably "true" within some range, "reasonable"
must be understood here to refer to some different kind of
judgment, one that it would make sense to apply to a review
of methodology as
635 well as of assumptions.
Since the methodology is a subject of technical judgment
within a recognized professional discipline, it would make
sense to judge the reasonableness of a method by reference
to what the actuarial profession considers to be within the
scope of professional acceptability in making an unfunded
liability calculation.
Accordingly, an employer's burden to overcome the presumption
in question (by proof by a preponderance that the actuarial
assumptions and methods were in the aggregate unreasonable)
is simply a burden to show that the combination of methods
and assumptions employed in the calculation would not have
been acceptable to a reasonable actuary.
In practical terms it is a burden to show something
about standard actuarial practice, not about the accuracy
of a predictive calculation, even though consonance with professional
standards in making the calculation might justify confidence
that its results are sound.
As thus understood, the presumption
in question supports no due process objection. The
employer merely has a burden to show that an apparently unbiased
professional, whose obligations tend to moderate any claimed
inclination to come down hard on withdrawing employers, has
based a calculation on a combination of methods and assumptions
that falls outside the range of reasonable actuarial practice.
To be sure, the burden may not be so "mere"
when one considers that actuarial practice has been described
as more in the nature of an "actuarial art" than
a science, Keith Fulton & Sons v. New England Teamsters,
762 F.2d 1137, 1143 (CA1 1985) (en banc) (internal quotation
marks omitted), and that the employer's burden covers "technical
actuarial matters with respect to which there are often several
equally 'correct' approaches," Committee Print 20-21.
[FN20] But since
imprecision inheres
636
in the choice of actuarial methods and assumptions, the resulting
difficulty is simply in the nature of the beast.
Because it must fall on whichever party bears the burden
of persuasion on such an issue, at least where the interests
at stake are no more substantial than Concrete Pipe's are
here, its allocation to one party or another does not raise
an issue of due process.
See supra, at 2281.
FN20.
Indeed, our view of the problem of imprecision in reviewing
actuarial methods and assumptions seems to have been the very
reason for including the presumption in the statute.
The Senate Committee Report states that "[t]he
[Senate] Committee [on Labor and Human Resources] includes
the presumption to reduce the likelihood of dispute and delay
over technical actuarial matters with respect to which there
are often several equally 'correct' approaches.
Without such a presumption, a plan would be helpless
to resist dilatory tactics by a withdrawing employer -- tactics
that could, and could be intended to, result in prohibitive
collection costs to the plan." Committee Print 20-21.
IV
Concrete
Pipe argues next that, as applied, the MPPAA violates substantive
due process and takes Concrete Pipe's property without just
compensation, both in violation of the Fifth Amendment.
As to these issues, our decisions in Gray and Connolly
provide the principal guidance.
A
In
Gray we upheld the MPPAA against substantive due process challenge.
Unlike the employer in Gray, Concrete Pipe here has
no complaint that the MPPAA has been retroactively applied
by predicating liability on a withdrawal decision made before
passage of the statute.
To be sure, since there would be no withdrawal liability
without prewithdrawal contributions to the Plan, some of which
were made before the statutory enactment, some of the conduct
upon which Concrete Pipe's liability rests ante dates the
statute. But
this fact presents a far weaker premise for claiming a substantive
due process violation even than the Gray employer raised,
and rejection of Concrete Pipe's contention is compelled by
our decisions not only in Gray, but in Usery v. Turner Elkhorn
Mining Co., 428 U.S. 1, 96 S.Ct. 2882, 49 L.Ed.2d 752 (1976),
upon which the Gray Court relied.
637
" 'It is by now well established
that legislative Acts adjusting the burdens and benefits of
economic life come to the Court with a presumption of constitutionality,
and that the burden is on one complaining of a due process
violation to establish that the legislature has acted in an
arbitrary and irrational way.
See, e.g., Ferguson v. Skrupa, 372 U.S. 726 [83 S.Ct.
1028, 10 L.Ed.2d 93] (1963);
Williamson v. Lee Optical Co., 348 U.S. 483, 487-488
[75 S.Ct. 461, 464, 99 L.Ed. 563] (1955).
"
'[I]t may be that the liability imposed by the Act ... was
not anticipated at the time of actual employment.
But our cases are clear that legislation readjusting
rights and burdens is not unlawful solely because it upsets
otherwise settled expectations.
See Fleming v. Rhodes, 331 U.S. 100 [67 S.Ct. 1140,
91 L.Ed. 1368] (1947);
Carpenter v. Wabash R. Co., 309 U.S. 23 [60 S.Ct. 416,
84 L.Ed. 558] (1940);
Norman v. Baltimore & Ohio R. Co., 294 U.S. 240
[55 S.Ct. 407, 79 L.Ed. 885] (1935);
Home Bldg. & Loan Assn. v. Blaisdell, 290 U.S.
398 [54 S.Ct. 231, 78 L.Ed. 413] (1934); Louisville & Nashville
R. Co. v. Mottley, 219 U.S. 467 [31 S.Ct. 265, 55 L.Ed. 297]
(1911). This is true even though the effect of the legislation
is to impose a new duty or liability based on past acts.
See Lichter v. United States, 334 U.S. 742 [68 S.Ct.
1294, 92 L.Ed. 1694] (1948);
Welch v. Henry, 305 U.S. 134 [59 S.Ct. 121, 83 L.Ed.
87] (1938); Funkhouser
v. Preston Co., 290 U.S. 163 [54 S.Ct. 134, 78 L.Ed. 243]
(1933).' " Gray,
467 U.S., at 729-730, 104 S.Ct., at 2718, quoting Turner Elkhorn,
supra, 428 U.S., at 15‑16, 96 S.Ct., at 2892 (footnotes
omitted).
To
avoid this reasoning, Concrete Pipe relies not merely on a
claim of retroactivity, but on one of irrationality.
Since the company contributed to the plan for only
3 1/2 years, it argues, none of its employees had earned vested
benefits through employment by Concrete Pipe at the time of
its withdrawal.
See Brief for Petitioner 28.
Concrete Pipe argues that, consequently, no rational
relationship exists between its payment of past contributions
and the imposition of liability for a share of the unfunded
vested benefits.
But
this argument simply ignores the nature of multiemployer plans,
which, as we have said above, operate by
638 pooling contributions and liabilities.
An employer's contributions are not solely for the
benefit of its employees or employees who have worked for
it alone. Thus,
Concrete Pipe's presupposition that none of its employees
had vested benefits at the time of its withdrawal may be wrong.
An employee whose benefits had vested before coming
to work for Concrete Pipe may have earned additional vested
benefits by the subsequent covered service.
Another may have had sufficient prior service credit
to obtain vesting of benefits during employment at Concrete
Pipe. A
third may have attained vesting while working for other employers
but based in part on service credits earned at Concrete Pipe.
But
even if Concrete Pipe is correct and none of its employees
had earned enough service credits for entitlement to vested
benefits by the time of Concrete Pipe's withdrawal, as a Concrete
Pipe employee each had earned service credits that could be
built upon in future employment with any other participating
employer. In
determining whether the imposition of withdrawal liability
is rational, then, the relevant question is not whether a
withdrawing employer's employees have vested benefits, but
whether an employer has contributed to the plan's probable
liability by providing employees with service credits.
When the withdrawing employer's
liability to the plan is based on the proportion of the
plan's contributions (and coincident service credits) provided
by the employer during the employer's participation in the
plan, the imposition of withdrawal liability is clearly rational.
It is true that, depending on
the future employment of Concrete Pipe's former employees,
the withdrawal liability assessed against Concrete Pipe may
amount to more (or less) than the share of the Plan's liability
strictly attributable to employment of covered workers at
Concrete Pipe.
But this possibility was exactly what Concrete Pipe
accepted when it joined the Plan.
A multiemployer plan has features of an insurance scheme
in which employers spread the risk that their employees will
meet the plan's vesting requirements
639
and obtain an entitlement to benefits.
A rational employer hopes that its employees will vest
at a rate above the average for all employees of contributing
employers, and that, in this way, it will pay less than it
would have by creating a single-employer plan.
But the rational employer also appreciates the foreseeable
risk that circumstances may produce the opposite result. [FN21]
Since the MPPAA spreads the unfunded vested liability
among employers in approximately the same manner that the
cost would have been spread if all of the employers participating
at the time of withdrawal had seen the venture through, the
withdrawal liability is consistent with the risks assumed
on joining a plan (however inconsistent that liability may
be with the employer's hopes).
In any event, under the deferential standard of review
applied in substantive due process challenges to economic
legislation there is no need for mathematical precision in
the fit between justification and means. See Turner Elkhorn,
428 U.S., at 19, 96 S.Ct., at 2894.
FN21.
An employer's calculation whether to join a plan will include
these factors as well as a determination of the other benefits
it can hope to receive from its participation in the plan.
See supra, at 2271.
Concrete
Pipe's substantive due process claim is not enhanced by its
argument that the MPPAA imposes obligations upon it contrary
to limitations on liability variously contained in the 1962
Trust Agreement, [FN22] in a collective-640
bargaining agreement between the Laborers
and multiemployer associations (the "1977-1980 Laborer's
Craft Master Labor Agreement") [FN23] and in an appendix
to the "Southern California Master Labor Agreements in
1977‑1980."
[FN24] Even
assuming that all
these provisions apply to Concrete Pipe, [FN25] its argument
runs against the holding in Gray that federal economic legislation,
which is not subject to constraints coextensive
641
with those imposed upon the States by
the Contract Clause of Art. I, § 10, of the Federal Constitution,
Gray, 467 U.S., at 733, 104 S.Ct., at 2719;
United States Trust Co. of N.Y. v. New Jersey, 431
U.S. 1, 17, n. 13, 97 S.Ct. 1505, 1515, n. 13, 52 L.Ed.2d
92 (1977), is subject to due process review only for rationality,
which, as we have said, is satisfied in the application of
the MPPAA to Concrete Pipe.
FN22.
The 1962 Trust Agreement states:
"
'Section 4.07. Neither
the Association or (sic) any officer, agent, employee or (sic)
committee member of the Associations shall be liable to make
Contributions to the Fund or with respect to the Pension Plan,
except to the extent that he or it may be an Individual Employer
required to make Contributions to the Fund with respect to
his or its own individual or joint venture operations, or
to the extent he may incur liability as a Trustee as hereinafter
provided. The liability of
any Individual Employer to the Fund, or with respect to the
Pension Plan, shall be limited to the payments required by
the Collective Bargaining Agreements with respect to his or
its individual or joint venture operations, and in no event
shall he or it be liable or responsible for any portion of
the Contributions due from other Individual Employers with
respect to the operations of such Individual Employers.
The Individual Employers shall not be required to make
any further payments or Contributions to the cost of operation
of the Fund or of the Pension Plan, except as may be hereafter
provided in the Collective Bargaining Agreements. " 'Section
4.08. Neither
the Associations, any Individual Employer, the Union, any
Local Union, nor any Employee shall be liable or responsible
for any debts, liabilities or obligations of the Fund or the
Trustees.' " App. 80-81, 32.
FN23. Article
X, § E(4) of the 1977-1980 Laborers' Craft Master Labor Agreement
provides: " 'The parties recognize and agree that the
Pension Trust and Plan was created, negotiated, and is intended
to continue to be if permitted by Law under ERISA, a defined
contribution plan and trust and that the individual Contractors'
liability with regard to the pension has been and remains
limited exclusively to payment of the contributions specified
from time to time in collective bargaining agreements.' "
Id., at 82, 34.
FN24. Appendix
K to the Southern California Master Labor Agreements in 1977-1980
states:
" 'IMPORTANT.
PENSION
BENEFITS ARE NOT AND HAVE NEVER BEEN GUARANTEED.
THEY ARE PAYABLE ONLY TO THE EXTENT THAT THE FUND HAS
ASSETS TO PAY BENEFITS.
NEITHER YOUR EMPLOYER NOR YOUR UNION HAS ASSUMED ANY
LIABILITY, DIRECTLY OR INDIRECTLY, TO PROVIDE MONTHLY PENSION
BENEFITS. YOUR EMPLOYERS'S
SOLE OBLIGATION IS TO MAKE THE CONTRIBUTIONS CALLED FOR IN
ITS COLLECTIVE BARGAINING AGREEMENT. THE PENSION PLAN
HAS ALSO BEEN CONSIDERED BY THE EMPLOYERS, THE UNION AND THE
TRUSTEES TO BE A DEFINED CONTRIBUTION PLAN.' "
Id., at 81-82, 33.
FN25. The
Plan contends that the record does not reflect that the appendix
mentioned in the text was incorporated by reference into Concrete
Pipe's own collective-bargaining agreement.
See Brief for Respondent 10, n. 7.
Nor
does the possibility that trustee decisions made "before
[Concrete Pipe] entered [the Plan]" may have led to the
unfunded liability alter the constitutional calculus.
See Brief for Petitioner 31.
Concrete Pipe's decision to enter the Plan after any
such decisions were made was voluntary, and Concrete Pipe
could at that time have assessed any implications for the
Plan's future liability.
Similarly, Concrete Pipe cannot rely on any argument
based on the fact that, because it was not a member of any
of the contractors' associations represented among the Plan's
trustees, it had no control over decisions of the trustees
after it entered the Plan that may have increased the unfunded
liability. Again,
Concrete Pipe could have assessed the implications for future
liability of the identity of the trustees of the Plan before
it decided to enter. [FN26]
The imposition of withdrawal liability here is rationally
related to the terms of Concrete Pipe's participation in the
Plan it joined and that suffices for substantive due process
scrutiny of this economic legislation.
FN26. Even
if Concrete Pipe were represented, its representative, like
all the trustees, would be bound to act consistently with
the fiduciary duty owed by trustees to covered employees and
beneficiaries of the plan.
See 29 U.S.C. § 1104(a)(1).
B
Given that Concrete Pipe's due
process arguments are unavailing, "it would be surprising
indeed to discover" the challenged statute nonetheless
violating the Takings Clause.
Connolly, 475 U.S., at 223, 106 S.Ct., at 1025.
Nor is there any violation.
Following the analysis in Connolly, we begin with the
contractual provisions relied upon from the Trust Agreement
and 642
the collective-bargaining agreements, which we find no more
helpful to Concrete Pipe than those adduced in the facial
challenge brought in Connolly, as described in that opinion:
"By
the express terms of the Trust Agreement and the Plan, the
employer's sole obligation to the Pension Trust is to pay
the contributions required by the collective-bargaining agreement.
The Trust Agreement clearly states that the employer's
obligation for pension benefits to the employee is ended when
the employer pays the appropriate contribution to the Pension
Trust. This
is true even though the contributions agreed upon are insufficient
to pay the benefits under the Plan."
Id., at 218, 106 S.Ct., at 1022 (citations and footnotes
omitted).
Indeed, one provision
of the Trust Agreement on which Concrete Pipe primarily relies
is substantially identical to the one at issue in Connolly.
Compare n. 22, supra, with Connolly, supra, at 218,
n. 2, 106 S.Ct., at 1022, n. 2.
We
said in Connolly that
"[a]ppellants'
claim of an illegal taking gains nothing from the fact that
the employer in the present litigation was protected by the
terms of its contract from any liability beyond the specified
contributions to which it had agreed.
'Contracts, however express, cannot fetter the constitutional
authority of Congress.
Contracts may create rights of property, but when contracts
deal with a subject matter which lies within the control of
Congress, they have a congenital infirmity.
Parties cannot remove their transactions from the reach
of dominant constitutional power by making contracts about
them.'
"If
the regulatory statute is otherwise within the powers of Congress,
therefore, its application may not be defeated by private
contractual provisions."
475 U.S., at 223-224, 106 S.Ct., at 1025 (citations
omitted).
643
Nothing has changed since these words
were first written. [FN27]
FN27.
To the extent that Concrete Pipe's argument could be characterized
as a challenge to the determination that, notwithstanding
the contractual language, it is a "defined benefits plan"
under the statute, this is a question on which Concrete Pipe
did not seek review.
See supra, at 2271.
Following
Connolly, the next step in our analysis is to subject the
operative facts, including the facts of the contractual relationship,
to the standards derived from our prior Takings Clause cases.
See id., at 224-225, 106 S.Ct., at 1026.
They have identified three factors with particular
significance for assessing the results of the required "ad
hoc, factual inquir [y] into the circumstances of each particular
case." Id.,
at 224, 106 S.Ct., at 1026.
The first is the nature of the governmental action.
Again, our analysis in Connolly applies with equal
force to the facts before us today.
"[T]he
Government does not physically invade or permanently appropriate
any of the employer's assets for its own use.
Instead, the Act safeguards the participants in multiemployer
pension plans by requiring a withdrawing employer to fund
its share of the plan obligations incurred during its association
with the plan.
This interference with the property rights of an employer
arises from a public program that adjusts the benefits and
burdens of economic life to promote the common good and, under
our cases, does not constitute a taking requiring Government
compensation."
Id., at 225, 106 S.Ct., at 1026.
We reject Concrete Pipe's contention
that the appropriate analytical framework is the one employed
in our cases dealing with permanent physical occupation or
destruction of economically beneficial use of real property.
See Lucas v. South Carolina Coastal Council, 505 U.S. 1003,
1015, 112 S.Ct. 2886, 2890-2892, 120 L.Ed.2d 798 (1992).
While Concrete Pipe tries to shoehorn its claim into
this analysis by asserting that "[t]he property of [Concrete
Pipe] which is taken, is taken in its entirety," Brief
for Petitioner
[644] 37, we rejected this analysis
years ago in Penn Central Transp. Co. v. New York City, 438
U.S. 104, 130-131, 98 S.Ct. 2646, 2662, 57 L.Ed.2d 631 (1978),
where we held that a claimant's parcel of property could not
first be divided into what was taken and what was left for
the purpose of demonstrating the taking of the former to be
complete and hence compensable.
To the extent that any portion of property is taken,
that portion is always taken in its entirety;
the relevant question, however, is whether the property
taken is all, or only a portion of, the parcel in question.
Accord, Keystone Bituminous Coal Assn. v. DeBenedictis,
480 U.S. 470, 497, 107 S.Ct. 1232, 1248, 94 L.Ed.2d 472 (1987)
("[O]ur test for regulatory taking requires us to compare
the value that has been taken from the property with the value
that remains in the property, [and] one of the critical questions
is determining how to define the unit of property 'whose value
is to furnish the denominator of the fraction' ") (citation
omitted).
There is no more merit in Concrete
Pipe's contention that its property is impermissibly taken
"for the sole purpose of protecting the PBGC [a government
body] from being forced to honor its pension insurance."
Brief for Petitioner 38;
see also Brief for Midwest Motor Express, Inc., et
al. as Amici Curiae 12.
That the solvency of a pension trust fund may ultimately
redound to the benefit of the PBGC, which was set up in part
to guarantee benefits in the event of plan failure, is merely
incidental to the primary congressional objective of protecting
covered employees and beneficiaries of pension trusts like
the Plan. "[H]ere,
the United States has taken nothing for its own use, and only
has nullified a contractual provision limiting liability by
imposing an additional obligation that is otherwise within
the power of Congress to impose."
Connolly, supra, 475 U.S., at 224, 106 S.Ct. at 1025‑-026.
Nor
is Concrete Pipe's argument about the character of the governmental
action strengthened by the fact that Concrete Pipe lacked
control over investment and benefit decisions that may have
increased the size of the unfunded vested liability.
The response to the same argument raised
645 under the substantive Due Process
Clause is appropriate here:
although Concrete Pipe is not itself a member of any
of the management associations that are represented among
the trustees of the fund, Concrete Pipe voluntarily chose
to participate in the Plan, notwithstanding this fact.
See supra, at 2289, and n. 26.
As
to the second factor bearing on the taking determination,
the severity of the economic impact of the Plan, Concrete
Pipe has not shown its withdrawal liability here to be "out
of proportion to its experience with the plan," 475 U.S.,
at 226, 106 S.Ct., at 1026, notwithstanding the claim that
it will be required to pay out 46% of shareholder equity.
As a threshold matter, the Plan contests this figure,
arguing that Concrete Pipe, a wholly owned subsidiary of Concrete
Pipe & Products Co., Inc., was simply "formed to
facilitate the purchase ... of certain assets of Cen-Vi-Ro,"
Brief for Respondent 2, and that the relevant issue turns
on the diminution of net worth of the parent company, not
Concrete Pipe.
See Tr. of Oral Arg. 29.
But this dispute need not be resolved, for even assuming
that Concrete Pipe has used the appropriate measure in determining
the portion of net worth required to be paid out, our cases
have long established that mere diminution in the value of
property, however serious, is insufficient to demonstrate
a taking. See, e.g., Village
of Euclid v. Ambler Realty Co., 272 U.S. 365, 384, 47 S.Ct.
114, 117, 71 L.Ed. 303 (1926) (approximately 75% diminution
in value); Hadacheck v. Sebastian, 239 U.S. 394, 405, 36 S.Ct.
143, 143, 60 L.Ed. 348 (1915) (92.5% diminution).
The final factor is the degree
of interference with Concrete Pipe's
"reasonable investment-backed expectations."
475 U.S., at 226, 106 S.Ct., at 1027.
Again, Connolly controls.
At the time Concrete Pipe purchased Cen-Vi-Ro and began
its contributions to the Plan, pension plans had long been
subject to federal regulation, and " '[t]hose who do
business in the regulated field cannot object if the legislative
scheme is buttressed by subsequent amendments to achieve the
legislative end.' FHA
v. The Darlington, Inc., 358 U.S. 84, 91, 79 S.Ct. 141, 146,
3 L.Ed.2d 132 (1958).
See 646
also Usery v. Turner Elkhorn Mining
Co., 428 U.S., at 15-16, 96 S.Ct., at 2892 and cases cited
therein." Id.,
475 U.S., at 227, 106 S.Ct., at 1027. Indeed, at that time
the Plan was already subject to ERISA, and a withdrawing employer
faced contingent liability up to 30% of its net worth.
See 29 U.S.C. § 1364 (1976 ed.);
see also 29 U.S.C. § 1362(b) (1976 ed.); Connolly,
supra, at 226‑227, 106 S.Ct., at 1027;
Gray, 467 U.S., at 721, 104 S.Ct., at 2713.
Thus while Concrete Pipe argues that requiring it to
pay a share of promised benefits "ignores express and
bargained‑for conditions on [its contractual] promises,"
Connolly, 475 U.S., at 235, 106 S.Ct., at 1031 (O'CONNOR,
J., concurring), it could have had no reasonable expectation
that it would not be faced with liability
for promised benefits.
Id., at 227, 106 S.Ct., at 1027 (opinion of the Court).
Because "legislation readjusting rights and burdens
is not unlawful solely because it upsets otherwise settled
expectations ... even though the effect of the legislation
is to impose a new duty or liability based on past acts,"
Turner Elkhorn, 428 U.S., at 16, 96 S.Ct., at 2983, Concrete
Pipe's reliance on ERISA's original limitation of contingent
liability to 30% of net worth is misplaced, [FN28] there being
no reasonable basis to expect that the legislative ceiling
would never be lifted. [FN29]
FN28.
See Brief for Petitioner 36-37 ("The ERISA contingent
liabilities were substantially different in scope from the
liabilities of MPPAA so that [Concrete Pipe] had no reasonable
notice that 46% of its net worth would be seized").
Justice
O'CONNOR does not join the statement to which this footnote
is attached.
FN29.
Nor do the contractual provisions on which Concrete Pipe would
rely provide the support it seeks.
Indeed, one such provision, Article X, § E(4) of the
1977-1980 Laborers' Craft Master Labor Agreement, provides
that liability will be limited to contributions specific in
collective-bargaining agreements "if permitted by law
under ERISA."
App. 82, ¶ 34.
"The
employe[r] in the present litigation voluntarily negotiated
and maintained a pension plan which was determined to be within
the strictures of ERISA."
Connolly, supra, 475 U.S., at 227, 106 S.Ct., at 1027.
In light of the relationship between Concrete Pipe
and the Plan, we find no basis to conclude that Concrete Pipe
is 647
being forced to bear a burden "which,
in all fairness and justice, should be borne by the public
as a whole." Armstrong v. United States, 364 U.S. 40,
49, 80 S.Ct. 1563, 1569, 4 L.Ed.2d 1554 (1960).
V
Having
concluded that the statutory presumptions work no deprivation
of procedural due process, and that the statute, as applied
to Concrete Pipe, violates no substantive constraint of the
Fifth Amendment, we affirm the judgment of the Court of Appeals.
It
is so ordered.
Justice
O'CONNOR, concurring.
I
join all of the Court's opinion, except for the statement
that petitioner cannot "rel[y] on ERISA's original limitation
of contingent liability to 30% of net worth."
Ante, at 2292.
The Court's reasoning is generally consistent with
my own views about retroactive withdrawal liability, which
I explained in Connolly v. Pension Benefit Guaranty Corporation,
475 U.S. 211, 228‑236, 106 S.Ct. 1018, 1027‑1032,
89 L.Ed.2d 166 (1986) (concurring opinion), and which I need
not restate at length here.
In essence, my position is that the "imposition
of this type of retroactive liability on employers, to be
constitutional, must rest on some basis in the employer's
conduct that would make it rational to treat the employees'
expectations of benefits under the plan as the employer's
responsibility."
Id., at 229, 106 S.Ct., at 1027.
The
Court does not hold otherwise. Rather, it reasons
that, although "the withdrawal liability assessed against
Concrete Pipe may amount to more ... than the share of the
Plan's liability strictly attributable to employment of covered
workers at Concrete Pipe," this possibility "was
exactly what Concrete Pipe accepted when it joined the Plan."
Ante, at 2288.
I agree that a withdrawing employer can be held responsible
for its statutory "share" of unfunded vested benefits
if the employer should have anticipated the prospect of withdrawal
liability when it joined the plan. In
such a 648 case,
the "basis in the employer's conduct that would make
it rational to treat the employees' expectations of benefits
under the plan as the employer's responsibility" would
be the very act of joining the plan.
I
am not sure that petitioner did in fact "accept"
the prospect of withdrawal liability when it joined the Construction
Laborers Pension Trust (Plan) in 1976.
As of that date, Congress had not yet promulgated the
Multiemployer Pension Plan Amendments Act of 1980 (MPPAA);
the kind of "withdrawal liability" imposed
on petitioner did not yet exist.
Although the Employee Retirement Income Security Act
of 1974 (ERISA) was in effect, and did create a contingent
liability for the employer that withdrew from a multiemployer
defined benefit plan, such liability was limited to 30% of
the employer's net worth.
See 29 U.S.C. §§ 1364, 1362(b)(2) (1976 ed.). Petitioner's
withdrawal liability under the MPPAA amounts to 46% of its
net worth. See
ante, at 2291.
In addition, the Plan apparently is a hybrid "Taft‑Hartley"
plan, which provides for fixed employee benefits and fixed
employer contributions. It remains an open
question whether hybrid Taft‑ Hartley plans are indeed
"defined benefit" rather than "defined contribution"
plans, and therefore subject to withdrawal liability.
See Connolly, supra, at 230, 232-235, 106 S.Ct., at
1028-1029, 1029-1035 (O'CONNOR, J., concurring).
We do not decide that question today.
See ante, at 2271, 2290, n. 27.
But
petitioner has not argued that its withdrawal liability, even
if otherwise permissible, cannot exceed the 30% cap that was
in effect in 1976.
Nor has petitioner claimed that the Plan is a defined
contribution plan.
In short, petitioner has failed to adduce the two features
of this case that might have demonstrated why it did not "accept"
the prospect of full withdrawal liability when it joined the
Plan. I therefore agree
with the Court's result as well as most of its reasoning.
I
cannot, however, agree that petitioner is precluded from "rely[ing]
on ERISA's original limitation of contingent liability to
30% of net worth."
Ante, at 2292.
The Court seizes
649 upon a passing reference in
petitioner's brief, see ante, at 2292, n. 28, to justify issuing
this unnecessary statement about a difficult issue that the
parties essentially have ignored.
I would not decide without adversary briefing and argument
whether ERISA's 30% cap might prevent retroactive withdrawal
liability above 30% of the employer's net worth for an employer
that joined a multiemployer plan after the passage of ERISA
but before the passage of the MPPAA.
I also note that the Court's opinion should not be
read to imply that employers may be subjected to retroactive
withdrawal liability simply because "pension plans [have]
long been subject to federal regulation." Ante, at 2291.
Surely the employer that joined a multiemployer plan
before ERISA had been promulgated -- before Congress had made
employers liable for unfunded benefits -- might have a strong
constitutional challenge to retroactive withdrawal liability.
The issue is not presented here -- again, petitioner
joined the Plan after the passage of ERISA -- and the Court
does not address it.
It remains to be resolved in a future case.
Justice
THOMAS, concurring in part and concurring in the judgment.
I
join all of the Court's opinion except Part III-B-1 -- the
portion of the opinion in which the Court grapples with the
trustee presumption in 29 U.S.C. § 1401(a)(3)(A).
The Court finds the presumption "incoherent with
respect to the degree of probability of error required of
the employer to overcome a factual conclusion made by the
plan sponsor."
Ante, at 2281. And because, in the Court's view, "there
would be a substantial question of procedural fairness under
the Due Process Clause" if employers had to show that
sponsors' findings were unreasonable or clearly erroneous,
ante, at 2281, the Court proceeds to interpret the statute
as if it required an unconstrained evidentiary hearing into
"any factual issue" concerning the employer's withdrawal
liability, ante, at 2283.
650 Until
today, § 1401(a)(3)(A) provided:
"For
purposes of any [arbitration] proceeding under this section,
any determination made by a plan sponsor under sections
1381 through 1399 of this title and section 1405 of this
title is presumed correct unless the party contesting the
determination shows by a preponderance of the evidence that
the determination was unreasonable or clearly erroneous."
(Emphasis added.)
Now the statute provides, in
effect, that "any factual determination made by a plan
sponsor shall be rejected by the arbitrator if the party contesting
the determination shows by a preponderance of the evidence
that the determination was erroneous."
There is no meaningful presumption of correctness and
no examination for reasonableness or clear error.
I decline to participate in this redrafting of a federal
law.
As
I see it, there are three missteps in the analysis.
First, the Court believes the statutory text is "incomprehensib[le],"
ante, at 2281, because it refers to three different, and mutually
inconsistent, "degree[s] of certainty," ante, at
2279, or of "probability," ante, at 2281.
This is incorrect -- in large part because the Court
overlooks the grammatical structure of the statute.
Section 1401(a)(3)(A) sets up no parallelism between
the phrase "by a preponderance of the evidence,"
which establishes the standard of proof for the arbitration
proceeding, and the critical terms "unreasonable"
and "clearly erroneous."
"[B]y a preponderance of the evidence" (emphasis
added) is an adverbial phrase that modifies the "show[ing]"
required of the employer. "Unreasonable"
and "clearly erroneous," on the other hand, are
predicate adjectives used to describe what it is the employer
must show.
The
incoherence identified by the Court follows from the assumption
that Congress has "confus[ed]" burdens of proof
with standards of review.
Ante, at 2280.
The Court believes that the terms "clearly erroneous"
and "unreasonable" must signify standards of review.
Ante, at 2279-2280. Standards of proof and standards
of review are entirely unrelated
651 concepts (as the Court intimates, see ante, at 2279-2281).
The Court's reading leads to the conclusion that §
1401(a)(3)(A) is "meaningless," ante, at 2280, because
the statute (as so interpreted) "defines the nature of
the conclusion the arbitrator must draw by using a combination
of terms that are categorically ill‑matched," ante,
at 2280. [FN*]
FN*
Regrettably, the Court compounds and further muddles the textual
difficulty by suggesting that in some sense, "preponderance
of the evidence," "unreasonable," and "clearly
erroneous" are comparable -- that they all refer to relative
"degree[s] of certainty."
Ante, at 2279. There is, in fact, no basis for comparing
any particular standard of proof with any particular standard
of review. An
appellate tribunal could be required to determine whether
it was "clearly erroneous" to find a disputed fact
"by a preponderance of the evidence," or it could
ask whether any "reasonable" factfinder could have
found "probable cause" to believe, or "clear
and convincing evidence" supporting, the fact in question.
See, e.g., Anderson v. Liberty Lobby, Inc., 477 U.S.
242, 252, 106 S.Ct. 2505, 2512, 91 L.Ed.2d 202 (1986) ("If
the defendant in a ... civil case moves for summary judgment
or for a directed verdict ..., [the inquiry is] whether
reasonable jurors could find by a preponderance of the evidence
that the plaintiff is entitled to a verdict") (emphasis
added); Jackson
v. Virginia, 443 U.S. 307, 318-319, 99 S.Ct. 2781, 2788-2789,
61 L.Ed.2d 560 (1979) ("[T]he critical inquiry on review
of the sufficiency of the evidence to support a criminal conviction
... is whether [a] rational trier of fact could have found
the essential elements of the crime beyond a reasonable doubt")
(emphasis added).
Any combination of evidentiary and review standards
is possible.
The
Court's preoccupation with standards of review is understandable,
at least with respect to "clearly erroneous," a
term with an established legal usage. See Anderson v. Bessemer
City, 470 U.S. 564, 573-575, 105 S.Ct. 1504, 1511-1512, 84
L.Ed.2d 518 (1985);
Fed.Rule Civ.Proc. 52(a).
But such a reading is not compelled.
As used in this statutory provision, "unreasonable"
and "clearly erroneous" cannot signify standards
applicable to the review of prior findings, since the arbitrator
himself is undeniably a factfinder, not an appellate tribunal.
See § 1401(c) (establishing a presumption of correctness
for "the findings of fact made by the arbitrator").
That the arbitrator is to undertake his examination
"by a preponderance of the evidence" explicitly
establishes his role as factfinder;
appellate review 652 does not occur "by"
a taking of "evidence." The
Court sees the arbitrator as a "hybrid," who acts
as both a trier of fact and a reviewer of facts found.
Ante, at 2279‑2280.
But the presumption of correctness that applies to
the plan sponsor's determinations does not make the arbitrator
a "reviewing body," ante, at 2280, any more than
the presumption of innocence in a criminal trial renders the
jury a reviewer, rather than a trier, of fact.
The
way out of the conundrum is apparent.
The terms "unreasonable" and
"clearly erroneous" must refer to what are,
in effect, elements of the employer's claim in the arbitration
proceeding. To
prevail in its action before the arbitrator, in other words,
the employer must show by a preponderance of the evidence,
first, that the plan sponsor has made a determination under
one of the relevant provisions and, second, that that determination
was either unreasonable or clearly erroneous.
This construction requires us to put aside the technical
definition of "clearly erroneous" and focus on the
literal meaning of the phrase.
"Clear" error can simply mean an obvious,
plain, gross, significant, or manifest error or miscalculation.
See Black's Law Dictionary 250 (6th ed. 1990).
That may not be the most natural reading (for a court,
that is) of this legal term of art, but if we do not drop
the assumption that "clearly erroneous" must be
a reference to the Bessemer City standard of review, we cannot
avoid the incoherence that has trapped the majority. The term "unreasonable,"
of course, is even more readily construed to refer to something
other than a standard of review, since it can hardly be thought
to have a sharply defined meaning that is limited to the context
of appellate review.
There is, for example, nothing unusual about requiring
a party to show as an element of a substantive claim that
something -- an interstate carrier's filed rate, for example,
see Reiter v. Cooper, 507 U.S. 258, 113 S.Ct. 1213, 122 L.Ed.2d
604 (1993) -- is "unreasonable."
Section 1401(a)(3)(A) is thus susceptible of a reading
that gives it a coherent meaning.
653
This interpretation also conforms neatly with the very similar
language and structure of the actuarial presumption in § 1401(a)(3)(B),
which the Court today finds unproblematic.
See ante, at 2284-2286.
That presumption provides that the actuary's determination
of unfunded vested benefits will be presumed correct unless
the employer shows "by a preponderance of the evidence"
that the actuarial assumptions and methods were "unreasonable"
or that the actuary made a "significant error."
The Court offers no persuasive explanation as to why
this presumption does not suffer from the same incoherence.
In addition, my reading of the term "clearly erroneous"
in § 1401(a)(3)(A) renders it virtually indistinguishable
from the term "significant error" in § 1401(a)(3)(B).
The
second false step in the Court's analysis is the use of the
rule of construction applied in Edward J. DeBartolo Corp.
v. Florida Gulf Coast Building & Constr. Trades Council,
485 U.S. 568, 575, 108 S.Ct. 1392, 1397-1398, 99 L.Ed.2d 645
(1988). Ante,
at 2282-2283.
This rule, which requires a court to adopt a reasonable
alternative interpretation of a statute when necessary to
avoid serious constitutional problems, does not provide authority
to construe the statute in a way that "is plainly contrary
to the intent of Congress."
DeBartolo, supra, at 575, 108 S.Ct., at 1397.
The rule "cannot be stretched beyond the point
at which [the alternative] construction remains 'fairly possible.'
" Public
Citizen v. Department of Justice, 491 U.S. 440, 481, 109 S.Ct.
2558, 2580, 105 L.Ed.2d 377 (1989) (KENNEDY, J., concurring
in judgment) (emphasis in original) (quoting Crowell v. Benson,
285 U.S. 22, 62, 52 S.Ct. 285, 296, 76 L.Ed. 598 (1932)).
"And it should not be given too broad a scope
lest a whole new range of Government action be proscribed
by interpretive shadows cast by constitutional provisions
that might or might not invalidate it."
Public Citizen, supra, 491 U.S., at 481, 109 S.Ct.,
at 2580. Here
it is plain, in my view, that Congress intended to shield
the plan sponsor's factual determinations behind a presumption
of correctness and intended that withdrawing employers would
have to show something more than simple error. The
654 Court's construction is plainly contrary to this intent
and is not "fairly
possible" under the terms of the statute.
Rather than a reasonable alternative reading, therefore,
the interpretation adopted by the Court today is effectively
a declaration that the statute as written is unconstitutional.
Which
leads to my final, and perhaps most fundamental, disagreement
with the Court.
Before a court can appropriately invoke the Crowell/DeBartolo
rule of construction, it must have a significantly higher
degree of confidence that the statutory provision would be
unconstitutional should the problematic interpretation be
adopted. The
potential due process problem troubling the Court is the supposed
lack of a neutral or "impartial" arbitration hearing.
Ante, at 2281.
This potential is based on an "assumption"
about a "risk" or "possibility" of trustee
bias, ante, at 2276, 2277 -- bias that, if it existed, might
be "preserve[d]" during the arbitration proceeding
by the presumption of correctness.
Ante, at 2278.
Petitioner has not established that the trustees were
biased in fact.
And whatever structural bias may flow from the trustees'
fiduciary obligations or from the fact that the trustees are
appointed by interested parties, see ante, at 2276-2277, will
likely be nullified by the elaborately detailed criteria that
channel and cabin their exercise of discretion.
See 29 U.S.C. §§ 1381-1399 (1988 ed. and Supp. III).
Such bias may be checked, in particular, by the requirement
of consistency that governs the trustees' choice of a method
for calculating liability.
See Keith Fulton & Sons, Inc. v. New England Teamsters
& Trucking Industry Pension Fund, Inc., 762 F.2d 1137,
1142 (CA1 1985) (en banc).
And the very fiduciary duty the trustees owe to the
fund should simultaneously prevent them from imposing excessive
withdrawal liability that will discourage other employers
from joining the fund in the future.
Id., at 1142-1143.
The Court does not consider these countervailing forces.
But
even if there is a real risk that structural bias may distort
the trustees' factual determinations, I am inclined
655 to believe that the arbitration proceeding -- presumption
and all -- provides adequate process for the employer.
Cf. Mathews v. Eldridge, 424 U.S. 319, 334-335, 96
S.Ct. 893, 902-903, 47 L.Ed.2d 18 (1976) (adequacy of specific
procedures involves consideration of private and public interests
and risk of erroneous deprivation).
This conclusion rests principally on the nature of
the particular statutory determinations to which the presumption
applies (those described in §§ 1381-1399 and 1405).
Many of these determinations, such as the mathematical
computations the trustees must perform under §§ 1386, 1388,
and 1391, involve little or no discretion.
As a result, the employer will have correspondingly
little difficulty proving the existence of any significant
error made by the trustees (either inadvertently or because
of bias). The
same can be said of withdrawal-date determinations under §§
1381 and 1383, especially where all the information relevant
to the determination is better known to the employer than
to the trustees.
To
me, the public interest is plain on the face of the statute:
Congress did not want withdrawing employers to avoid
their obligations by engaging in a lengthy arbitration over
relatively insignificant errors.
At the same time, the employer's interest in correcting
miscalculations that are significant is adequately protected
by the opportunity for arbitration afforded by § 1401.
For
these reasons, I concur only in the Court's judgment that
the application of § 1401(a)(3)(A) "did not deprive Concrete
Pipe of its right to procedural due process."
Ante, at 2283-2284.
|