Community Rights Counsel Community Rights Counsel Community Rights Counsel Community Rights Counsel

About CRC

Legal Resources

Community Rights Report Newsletter

Support Us

Newsroom

Redefining Federalism

Warming Law Blog


Community Rights Counsel
1301 Connecticut Avenue, NW, Suite 502
Washington, DC 20036
Phone: 202-296-6889
Fax: 202-296-6895


City of Monterey v. Del Monte Dunes at Monterey, Ltd.
BACKGROUND Del Monte Dunes

The Facts: The case involves a 37.6-acre parcel of environmentally sensitive, oceanfront property in Monterey, California at Del Monte Beach. The sand dunes on the property are among the largest and best preserved in central California. The property's native flora includes buckwheat, which is the natural habitat of the Smith's Blue Butterfly, a species listed as endangered under the federal Endangered Species Act.

In 1981, the previous owner of the property, Ponderosa Homes, applied to the City of Monterey for a permit to build a 344-unit residential complex on the property.

After denying several development proposals, the City Council approved a site plan for 190 units in 1984, subject to 15 conditions. The conditions included a requirement that the developer submit an adequate habitat restoration plan.

In late 1984, Del Monte Dunes at Monterey, Ltd. bought the property for $3.7 million, with full knowledge that development of the site was subject to the 15 conditions. Del Monte pursued final approval of the permit application by seeking to fulfil the conditions

In June 1986, the City denied the permit. The City Council listed six reasons for the denial, including th e significant harm to the environment expected from the development and the lack of adequate access to and from the property. During public hearings on the permit, regulatory agencies, environmental experts, city staff, and others advised the City that Del Monte's proposed habitat restoration plan would not adequately mitigate the environmental impact of the development.

In 1991, while the litigation was on-going, the State of California purchased the property for $4.5 million, $800,000 more than Del Monte had paid for the site in 1984. The $4.5 million purchase price was based on an appraisal that assumed that the highest and best use of the property is residential development with a density up to 150 units

The lawsuit: In late 1986, Del Monte filed suit in federal district court, alleging that the permit denial constituted a "taking" of private property under the Fifth Amendment that entitled Del Monte to just compensation. Del Monte also claimed that the denial violated the Equal Protection and Due Process Clauses of the Fourteenth Amendment. The parties argued for several years about whether Del Monte's claim was "ripe" for adjudication. In 1990, the Ninth Circuit Court of Appeals allowed Del Monte's suit to proceed. Viewing the facts in the light most favorable to Del Monte, the Ninth Circuit ruled that it would have been "futile" for Del Monte to make further permit applications.

The litigation proceeded to trial. The district court ruled for the City on the due process claim, concluding that the permit denial was "not arbitrary and irrational, but was for valid purposes." The trial record shows that regulatory agencies and many others advised the City that Del Monte's habitat restoration plan would not adequately mitigate the environmental im pact of the proposed development. Del Monte presented contrary evidence. The court found that the evidence before the City was "in conflict," there were "differences of opinion" regarding the proposed development's effect on the environment. It concluded that the City's resolution of the conflicting evidence was reasonable and its decision to deny the permit was "for valid regulatory reasons." The district court also specifically concluded, based on a full factual record presented at trial, that the City was "not attempting to forestall all reasonable development." Finally, the district court found that city staff and the city planning commission spent "exhaustive time and energy" on the proposal and that they engaged in "a sincere effort" to work with Del Monte on the proposal.

Notwithstanding these rulings, the court sent the takings claim to the jury, instructing the jury to rule for Del Monte if the permit denial either (1) deprived Del Monte of all economically viable use of the property, or (2) did not substantially advance a legitimate public purpose. The jury awarded Del Monte $1,450,000, without specifying which theory of takings liability it has accepted. The Ninth Circuit affirmed.

The City sought review in the U.S. Supreme Court on three issues: (1) whether the trial court erred in having a jury decide the takings claim; (2) whether the trial court erred in allowing the jury to reweigh the evidence concerning the reasonableness of the permit denial; and (3) whether the appeals court erred in ruling that a development permit denial must be "roughly proportional" to the harm expected from the proposed development. In March 1998, the Supreme Court agreed to review the case, and in October 1998 it heard oral argument.

Back

Back to CRC Home

If you have questions or comments about this website or
Community Rights Counsel email us!

© 2005 Community Rights Counsel. All rights reserved.